Mugardos LNG Terminal: 2nd Jetty
General Information
Promoter
Reganosa
Operator
Reganosa
Host Country
Spain
Status
Planned
Website
Publication Approval Status
Approved
Sponsors
Reganosa
100%
LNG-N-296
Project
LNG Terminal
Non-FID
Update Date
25/05/2016
Non-Advanced
Description
Construction of a second jetty for berthing of LNG ship with capacity from approximately 1,000m3 LNG up to 266,000m3 LNG.
Regulatory Decisions and
similar material conditions
Enabled Projects
Project Code Project Name
LNG-N-297 Mugardos LNG Terminal: Storage Extension
Schedule
Start Date
End Date
Pre-Feasibility
12/2014
Feasibility
12/2014
02/2015
FEED
03/2018
08/2018
Market Test
08/2018
Permitting
07/2018
12/2018
Supply Contracts
01/2019
FID
02/2019
Construction
03/2019
08/2020
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
No (The last aproved Spanish NDP ended
in 2016. The Royal Decree-Law 13/2012
cancel any award procedures of new
regasification plants in Spain.)
NDP Number
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 164 of 620
Current TYNDP : TYNDP 2017 - Annex A