Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Arc Lyonnais (GRTgaz section)

1,200

150

Barbaira - Border (TIGF section)

900

120

Barbaira CS (TIGF section)

7

Eridan (GRTgaz section)

1,200

220

Midi pipeline (GRTgaz section)

1,050

200

Midi pipeline (TIGF section)

1,050

40

Palleau CS (GRTgaz section)

New station

50

Perche (GRTgaz section)

900

63

St-Avit CS (GRTgaz section)

15

St-Martin de Crau CS

New station

30

Total

793

102

Schedule

Start Date

End Date

Pre-Feasibility

06/2012

Feasibility

03/2007

FEED

Market Test

06/2017

Permitting

Supply Contracts

FID

Construction

Commissioning

2024

2024

NDP and PCI Information

Part of NDP

Yes (GRTgaz and TIGF development plans

2015)

NDP Number

na

Currently PCI

Yes (5.5 - 5.8)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 199 of 620

Current TYNDP : TYNDP 2017 - Annex A