Expected Gas Sourcing

LNG ()

Benefits

Main Driver

Others

Main Driver Explanation

Developments of GRTgaz network required to offer firm capacity to the planned expansion of the LNG terminal at Montoir de Bretagne

Benefit Description

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

2 years

Delay Explanation

Waiting for terminal promoter decision

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

$UWqUH GX 0DLQH

Ending the looping of the pipeline

1,050

200

$UWqUH GX 3HUFKH

Ending the looping of the pipeline

900

63

Auvers-le-Hamon CS

Station adaptation

0

Total

263

0

Schedule

Start Date

End Date

Pre-Feasibility

12/2011

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

12/2022

Commissioning

2022

2022

NDP and PCI Information

Part of NDP

Yes (GRTgaz PDD 2015)

NDP Number

na

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 202 of 620

Current TYNDP : TYNDP 2017 - Annex A