Time Schedule

Grant Obtention Date

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

MI. The project will provide access to natural gas to countries/ regions without adequate access to it SoS. The project will provide a diversified

supply route Sustainability. The project will increase gas penetration in countries/regions where it will replace less environment friendly energy

sources

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Greek section

1,400

370

280

Total

370

280

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2020

2020

NDP and PCI Information

Part of NDP

No (The project is still on the maturing

phase and will be included in the NDP

in a later stage.)

Greek TS to TAP.)

NDP Number

Currently PCI

Yes (6.25.2)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 244 of 620