Expected Gas Sourcing

Caspian Region, Russia, LNG (?), The project may source gas from all gas sources supplying or transitting Greece

Technical Information (UGS)

Storage Facility

South Kavala

Storage Facility Type

Aquifer

Multiple-Cycle

Yes

Working Volume (mcm)

360.00

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

2 years

Delay Explanation

Decision on the procedure to select the project promoter and time needed to prepare the relevant tender procedure.

PCI Details

PCI Benefits

Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at

supplying directly or indirectly at least two Member States

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2022

2022

NDP and PCI Information

Part of NDP

No (The Project Promoter is not a

Transmission System Operator and as such

does not have the obligation to submit a

National Development Plan.)

NDP Number

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%