Table of Contents Table of Contents
Previous Page  582-583 / 1248 Next Page
Information
Show Menu
Previous Page 582-583 / 1248 Next Page
Page Background

Expected Gas Sourcing

LNG (?), it will be gas from Croatia transport system, Croatian UGS and all import routes (LNG and IAP)

Benefits

Main Driver

Market Demand

Main Driver Explanation

This gas pipeline passes only through the territory of the Republic of Croatia. However, it has regional significance since it is the main evacuation gas

pipeline from the LNG solution on the island of Krk towards Hungary and it is its main role. This gas pipeline increases utilisation of the interconnection

with Hungary so it has influence on Hungary but also further on Slovakia and Ukraine. The gas pipeline shall be also significant for third countries; Serbia,

Bosnia and Herzegovina by constructing interconnection with these countries.

Benefit Description

The project is the main gas pipeline for transport of LNG from the terminal on the island of Krk as well as from other possible sources, such as gas from

the Ionian-Adriatic Pipeline , towards CEE and SEE countries. At the same time, in addition to already constructed interconnection gas pipeline with

Hungary, Slobodnica-Donji Miholjac-Dravaszerdahely, it presents the Croatian part of the strategic transregional gas pipeline connection Adriatic-Baltic

the aim of which is to connect the Polish and Croatian LNG terminal. The most important impacts and benefits of this project: 1. It provides viable and

secure supply of CEE and SEE countries, which are heavily dependent on the Russian gas and jeopardized by the Russian giving up on the South Stream

project and the announcement regarding termination of gas transmission via Ukraine after 2019. 2. It provides diversification of supply (also in case the

previously mentioned threats fail to occur) and thereby competitiveness and lower price

Delay Explanation

This project completely depends on LNG terminal project on island of Krk

Barriers

Barrier Type

Description

Others

The project completly depends on the realisation of the Krk LNG project

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 288 of 620

Current TYNDP : TYNDP 2017 - Annex A