Expected Gas Sourcing
Black Sea
Time Schedule
Grant Obtention Date
14/10/2015
Delay Since Last TYNDP
3 year
Delay Explanation
Black Sea project delay
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
&VDQiGSDORWD
+1 Comressor unit 4.5MW
4
Total
4
Schedule
Start Date
End Date
Pre-Feasibility
06/2014
Feasibility
09/2016
07/2017
FEED
11/2018
04/2020
Market Test
12/2016
Permitting
05/2017
09/2018
Supply Contracts
04/2017
FID
10/2018
Construction
03/2021
12/2022
Commissioning
2022
2022
NDP and PCI Information
Part of NDP
Yes (Hungarian TYNDP 2015)
NDP Number
12.6.1.
Currently PCI
Yes (6.24.9.)
CBCA Decision
Yes (2016-10-06)
Market Survey
Open Season(2016-12-31)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 323 of 620
Current TYNDP : TYNDP 2017 - Annex A