Expected Gas Sourcing
Russia, LNG ()
PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Riga-Iecava-Lithuanian border
In case of lower market demand diameter of 500 mm can be
used
700
93
Total
93
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
No (National Development Plan for 2014-
2020 does not specify particular projects.
Under activity "Energy efficiency and
energy production" title "7.Development of
energy infrastructure networks" may
include project of enhancement of Latvia-
Lithuania interconnection)
NDP Number
Currently PCI
Yes (8.2.1)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 403 of 620
Current TYNDP : TYNDP 2017 - Annex A