PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Enabled Projects
Project Code Project Name
LNG-N-211 Connection of Malta to the European Gas Network - LNG Regasification
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Delimara (Malta) to Gela (Sicily) Italy
Length & diameter of interconnector have been updated
following results from pre-feasibility study completed in April
2015.
560
155
FSRU (Malta) to Delimara (Malta)
Diameter updated to reflect send-out capacity of offshore
FSRU.
560
12
Total
167
Schedule
Start Date
End Date
Pre-Feasibility
04/2015
Feasibility
04/2013
04/2015
FEED
08/2019
06/2020
Market Test
04/2019
Permitting
04/2017
06/2020
Supply Contracts
10/2021
FID
06/2020
Construction
05/2023
11/2025
Commissioning
2026
2026
NDP and PCI Information
Part of NDP
Yes (Malta National Reform Programme
April 2015 )
NDP Number
Section 3.4.2
Currently PCI
Yes (5.19)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM