Expected Gas Sourcing

Caspian Region, Norway, Russia, LNG ()

Benefits

Main Driver

Others

Main Driver Explanation

Regulation SoS and market integration

Benefit Description

Implementation of PL-CZ interconnection will have an impact on: increasing the security of gas supply, providing overall flexibility for the CEE region and

diversifying the supply routes for the CEE region; improving European gas grid interconnection; increasing the security and reliability of the cross-border

gas transmission between the Czech Republic and Poland (fulfilment of N-1 rule in Poland); creating a robust, well-functioning internal market in the

Czech Republic and Poland and promoting the competition; contributing to the creation of an integrated and competitive gas market in the CEE region;

establishing adequate technical conditions necessary to cover the forecasted growth of the gas demand in Poland based on the development of the

power generation sector and possible leverage for market coupling potential in Central-Eastern Europe.

Barriers

Barrier Type

Description

Permit Granting

Efficient permitting procedures are necessary for timely implementation of the project.

Political

Due to the project drivers which are mainly related to SoS in Central-Eastern Europe, the project does not meet the criterion of economic viability, so the

external co-financing is indispensable. Lack of external financial support may be a serious barrier in implementation.

Others

Due to the project drivers which are mainly related to SoS in Central-Eastern Europe, the project does not meet the criterion of economic viability, so the

external co-financing is indispensable. Lack of external financial support may be a serious barrier in implementation.