Immingham Storage Co Ltd – Immingham East Terminal
IME-SIS1 – Safety Instrument System Shutdown Conditions Proof Testing Procedure
P & I Design Ltd
DOCUMENT NO: SI483018_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 09.04.14
Tel: + 44 (0)1642 617444
PAGE 6 OF 17
Fax: + 44 (0)1642 616447
www.pidesign.co.uk5
PREPARATION
All Health and Safety / Permit To Work systems must be implemented before commencing
testing. SI483012_RPT - IME-SIS1 RAMS is to be submitted for approval prior to the site
testing.
IME-SIS1 is completely independent of the BPCS, no overrides or special preparations are
required to facilitate uncompromised testing.
Controlled copies of the following documentation will be required :-
SI483015_RPT - IME-SIS1 Operation, Maintenance and Modification Lifecycle
SI483018_RPT - IME-SIS1 Shutdown Conditions Proof Testing
SI483010_SCH - IME-SIS1 Instrument Schedule
SI483012_SCH - IME-SIS1 Trip Matrix
SI483001_DWG - Tanks 561, 564 & 568 Cable Overview
IME-K-0028 – Tank 561 P&ID
IME-K-0052 – Tank 564 P&ID
IME-K-0050 – Tank 568 P&ID
SI483017_RPT - IME-SIS1 Documentation Verification to be completed prior to each
period of testing to confirm correct revisions of documentation.
A controlled copy of this procedure will be used to carry out the testing and will form part of
the lifecycle testing documentation.
Controlled copies of all documentation required for testing to be attached. In addition to
procedures documented in this report calibration certificates, engineers reports are to be
issued to each item as applicable.