Immingham Storage Co Ltd – Immingham East Terminal

IME-SIS1 – Safety Instrument System Shutdown Conditions Proof Testing Procedure

P & I Design Ltd

DOCUMENT NO: SI483018_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 09.04.14

Tel: + 44 (0)1642 617444

PAGE 6 OF 17

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

5

PREPARATION

All Health and Safety / Permit To Work systems must be implemented before commencing

testing. SI483012_RPT - IME-SIS1 RAMS is to be submitted for approval prior to the site

testing.

IME-SIS1 is completely independent of the BPCS, no overrides or special preparations are

required to facilitate uncompromised testing.

Controlled copies of the following documentation will be required :-

SI483015_RPT - IME-SIS1 Operation, Maintenance and Modification Lifecycle

SI483018_RPT - IME-SIS1 Shutdown Conditions Proof Testing

SI483010_SCH - IME-SIS1 Instrument Schedule

SI483012_SCH - IME-SIS1 Trip Matrix

SI483001_DWG - Tanks 561, 564 & 568 Cable Overview

IME-K-0028 – Tank 561 P&ID

IME-K-0052 – Tank 564 P&ID

IME-K-0050 – Tank 568 P&ID

SI483017_RPT - IME-SIS1 Documentation Verification to be completed prior to each

period of testing to confirm correct revisions of documentation.

A controlled copy of this procedure will be used to carry out the testing and will form part of

the lifecycle testing documentation.

Controlled copies of all documentation required for testing to be attached. In addition to

procedures documented in this report calibration certificates, engineers reports are to be

issued to each item as applicable.