Immingham Storage Co Ltd – Immingham East Terminal

IME-SIS1 – Safety Instrument System Shutdown Conditions Proof Testing Procedure

P & I Design Ltd

DOCUMENT NO: SI483018_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 09.04.14

Tel: + 44 (0)1642 617444

PAGE 4 OF 17

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

3

SCOPE

Client / Company

-

Immingham Storage Co Ltd

Location / Facility

-

ISCo East Terminal

Plant Unit

-

Tanks 561, 564 & 568

Service

-

No4 East Storage Tank Overfill Protection

SIS Tag No

-

IME-SIS1

SIF’s Tag No’s

-

TK561-SIF1, TK564-SIF1 & TK568-SIF1

SIL

-

2

Lifecycle Stages

Operation and Maintenance -

BS EN 61511 Clause 16

Audience

This document has been produced for use by competent persons knowledgeable in testing

Safety Instrumented Systems.

Brief System Description

IME-SIS1 under test is to prevent the overfill of storage tanks 561, 564 & 568 when on

import duty. The system is classified as SIL2.

Full system description in documentation reference SI277001_RPT – IME-SIS1 Safety

Instrument System and Piping & Instrument Diagrams – IME-K-0028 – Tank 561, IME-K-

0052 – Tank 564 & IME-K-0050 – Tank 568.

Procedure

This procedure outlines the necessary steps required to verify the correct equipment is

installed, the physical condition of the installed equipment and the functional operation

performs the SIF’s as designed.

Detailed in this report are the methods of test for each SIF.

The results of these tests will be recorded in this report, historical data will be recorded and

approved as satisfactory in report reference SI483015_RPT - IME-SIS1 Operation,

Maintenance and Modification Lifecycle.

This report details shutdown condition testing whilst no transfer to the tanks is in operation.

All faults should be reported to the system keeper, with minor repairs carried out if

practicable. If further maintenance work is required the system keeper will initiate it.