CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 23 OF 123

and cost effective than preparing them separately. Having current master plans is important for obtaining future

grant funds as well as defining long term direction for the development of future citywide park, recreation, trail,

bicycle and pedestrian facilities. These master plans would be consistent with the General Plan Circulation

Element goals #1, #6, #7, #8, and #9.

Expenditure Schedule & Category

Parks & Recreation: 136014

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86201 - Environmental Clearances

$20,000

PROJECT COST

$20,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f301 - Park Impact Fund

$20,000

FUNDING TOTALS

$20,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

____

Project Design

Right-of-Way Acquisition &

Permitting

Construction

Project Closeout

____

Operating Cost Impacts

Updating the Plan will not create any additional operational costs. Ongoing operations and maintenance cost

planning for future park development will be a component of the Master Plan.