CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 21 OF 123

traveling north to Britton Middle School.

Project Justification

The City Council has made revitalization of the downtown through implementation of the Downtown Specific

Plan one of its priorities. The Downtown currently lacks green park spaces and construction of these parks will

support the Downtown Placemaking Investment Strategy.

Expenditure Schedule & Category

Parks & Recreation: 135013

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86120 - Property Acquisition

$126,000

86201 - Environmental Clearances

$75,000

86220 - Architecture and Design

$50,000

86360 - Construction

$3,600,000

86530 - Project Implementation

$200,000

PROJECT COST

$4,051,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f301 - Park Impact Fund

$3,801,000

f355 - School Pedestrian & Traffic

Safety

$250,000

FUNDING TOTALS

$4,051,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

Project Design

__

Right-of-Way Acquisition &

Permitting

__

Construction

_______

Project Closeout

____

Operating Cost Impacts

Having additional park lands in the City's inventory will bring additional maintenance costs. The costs are

estimated to be approximately $90,000 per year, beginning in 2016/17. Maintenance costs have been included in

the City Operating Budget's five year forecast.