CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 81 OF 123

Expenditure Schedule & Category

Water: 603000

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86200 - Professional Services

$35,000

86220 - Architecture and Design

$25,000

$25,000

$25,000

$25,000

86360 - Construction

$1,221,000

$160,000

$160,000

$160,000

$160,000

86530 - Project Implementation

$69,000

$15,000

$15,000

$15,000

$15,000

PROJECT COST

$1,325,000

$200,000

$200,000

$200,000

$200,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f651 - Water Impact Fund

$884,000

$200,000

$200,000

$200,000

$200,000

f653 - Water CIP Fund

$441,000

FUNDING TOTALS

$1,325,000

$200,000

$200,000

$200,000

$200,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

__

Project Design

_____

Right-of-Way Acquisition &

Permitting

Construction

_____

_____

_____

_____

_____

Project Closeout

__

Operating Cost Impacts

This project will increase maintenance and operating costs which will be offset by water sales in some instances.