CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 86 OF 123
Project
Water Main Replacement
Project No.
610000
Category
Water
Department
Public Works
Council Priorities
Enhancing Public Safety, Maintaining Fiscal
Responsibility
Location
Citywide
Project Description
The City has approximately 182 miles of water pipelines in its water distribution system ranging in age.
Replacement of aging pipelines is a routine, ongoing program.
In FY17/18 and FY18/19, the existing transmission main feeding the existing Holiday 1 & 2 Reservoirs will be
replaced to improve water storage capacity and fire protection for the surround area.
Future water main projects will be identified with the completion of the newWater System Master Plan in early
FY 16/17 as part of the General Plan Update. The budget below anticipates projects in future years and will be
updated once the new CIP is produced.
Project Justification
In order to ensure system reliability, the City's water mains are on a scheduled maintenance/ replacement
program.