CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 88 OF 123
Project
Recoat Water Reservoir/Tank
Project No.
620007
Category
Water
Department
Public Works
Council Priorities
Enhancing Public Safety, Maintaining Fiscal
Responsibility
Location
City Water Storage
Reservoirs
Project Description
The City has thirteen (13) water tanks/reservoirs that must be maintained in accordance with American Water
Works Association (AWWA) standards. A typical re-coating includes the removal of the old coating, application
of a new internal epoxy coating, corrosion-resistant paint on the exterior surface and structural repairs and
required upgrades.
In FY 21/22, the El Toro Tank rehabilitation will be finished, and repairs and stabilization to the access road (due to
it being adjacent to the hillside) will be completed.
Project Justification
The ongoing re-coating project is required for compliance with the City's Water System Operating permit issued
by the Department of Public Health. Each re-coating typically lasts for 15-25 years depending on the tank location
and other environmental factors.