CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 90 OF 123

Project

Water Supply Planning

Project No.

623014

Category

Water

Department

Public Works

Council Priorities

Enhancing Public Safety, Protecting the

Environment

Location

Citywide

Project Description

The City continues to face water supply challenges as drought conditions persist throughout much of California.

The City Council has directed staff to expand its water supply planning efforts to include use of recycled water,

stormwater capture, and to explore the use of other surface water supplies. This work began when with the

completion of the 2015 Morgan Hill Recycled Water Feasibility Evaluation which identified some of the challenges

of bringing recycled water to the City. This project would begin the planning and technical studies necessary to

position the City to use recycled water and stormwater for groundwater recharge. It will also look at securing

additional long term surface water supplies in cooperation with SCVWD and City of Gilroy. Some key tasks will

include:

o Identifying suitable groundwater recharge locations that meet indirect potable reuse regulatory requirements

o Groundwater modeling to evaluate flow patterns and impact of well pumping

o Tracer studies to determine groundwater travel times

o Identifying stormwater infiltration areas

o Technical and legal review of recycled water requirements

o Exploring municipal system expansion with well abandonment opportunities

o Options for long term surface water supply rights

The project would also plan for the acquisition of acceptable recharge sites once the sites were identified. The

planned start for land acquisition is in 2018.