CITY OF MORGAN HILL
CAPITAL IMPROVEMENT PROGRAM
2017-2022 Six-Year Capital Improvement Program
PAGE : 82 OF 123
Project
Booster Pump Rehabilitation
Project No.
607000
Category
Water
Department
Public Works
Council Priorities
Enhancing Public Safety. Maintaining Fiscal
Responsibility.
Location
City Booster Stations
Project Description
The City has an ongoing maintenance program for the repairs and updates for the City's ten (10) water booster
stations. Projects in FY 16/17 include the retrofit of the E. Dunne Booster Station. This project will reconfigure
the station to also serve the E. Dunne Hill Reservoir Water Main Project and the new 850,000 gallon reservoir
near Flaming Oaks Lane to support the new Hill Reservoir. This project will also support the FY15/16 Oak Canyon
Booster Station currently under construction. The combination of the new transmission main, the new reservoir
and modifications to the existing E. Dunne Booster station will significantly improve water storage capacity and
fire protection for the surround area.
A new CIP is being prepared as part of the new Water Master Plan to be completed in early FY 16/17. Future
booster pump station rehabilitation projects will be defined including scope and timing of the projects in the new
CIP. The spending plan below will be updated once the new project schedule is defined.
Project Justification
In order to ensure system reliability, the booster stations are on a scheduled maintenance program.