CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 82 OF 123

Project

Booster Pump Rehabilitation

Project No.

607000

Category

Water

Department

Public Works

Council Priorities

Enhancing Public Safety. Maintaining Fiscal

Responsibility.

Location

City Booster Stations

Project Description

The City has an ongoing maintenance program for the repairs and updates for the City's ten (10) water booster

stations. Projects in FY 16/17 include the retrofit of the E. Dunne Booster Station. This project will reconfigure

the station to also serve the E. Dunne Hill Reservoir Water Main Project and the new 850,000 gallon reservoir

near Flaming Oaks Lane to support the new Hill Reservoir. This project will also support the FY15/16 Oak Canyon

Booster Station currently under construction. The combination of the new transmission main, the new reservoir

and modifications to the existing E. Dunne Booster station will significantly improve water storage capacity and

fire protection for the surround area.

A new CIP is being prepared as part of the new Water Master Plan to be completed in early FY 16/17. Future

booster pump station rehabilitation projects will be defined including scope and timing of the projects in the new

CIP. The spending plan below will be updated once the new project schedule is defined.

Project Justification

In order to ensure system reliability, the booster stations are on a scheduled maintenance program.