Local Fuel plc – Shoreham Oil Terminal
Safety Instrumented Systems – Policy and Lifecycle Activities
P & I Design Ltd
DOCUMENT NO: LF364003_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: C DATE: 12.06.15
Tel: 00 44 (0)1642 617444
PAGE 10 OF 19
Fax: 00 44 (0)1642 616447
www.pidesign.co.uk5.7
Installation, Commissioning and Validation
Local Fuel plc or the System Integrator will employ sub-contractors to install the SIS. All
installation work will be carried out by technicians who are competent in both SIS and
hazardous areas working and will be undertaken by CompEx certified technicians, or at a
minimum the final inspections, prior to energising the system, must be carried out and
documented by a CompEx certified technician.
Local Fuel plc will ensure that the Installation Contractor has all required documentation in
order that the installation will comply with the design. It is the Installation Contractor’s
responsibility to ensure that any changes during the installation are advised and agreed with
the designer and supported with information to allow As Built documentation.
Installation testing documentation is to be provided by the Installation Contractor to Local
Fuel plc or their representative for inclusion into the Safety Instrumented System Manual.
On completion of the installation the full system will be pre-commissioned and validated to
ensure the installed SIS meets the requirement of the design for both functional safety and in
compliance with BS EN 61511.
Full and comprehensive records will be produced and retained of the installation,
commissioning and validation detailing test results, instrumentation calibration, procedures
used and any discrepancies between actual and expected results. This documentation will be
included in the Safety Instrumented System Manual.
As shown in Figure 1, validation of the Installation and Commissioning is required at this
lifecycle phase. The Functional Safety Manager is responsible to ensure that this validation is
completed as defined in the Safety Plan. Local Fuel plc have developed checklists to record
the verification of the validation process.
A Functional Safety Assessment (FSA) Stage 3 is to be performed. The Functional Safety
Manager will arrange for an assessment to be conducted.
5.8
Operation & Maintenance
To ensure that the functional safety of the SIS is maintained during operation and maintenance
Local Fuel plc. ensure that SIS/SIF are maintained, tested and inspected.
Inspection, maintenance and test procedures will be produced for the SIS. All testing will be
fully documented and analysed. Inspection, maintenance and test procedures should be
approved by the FSM.
The test procedures should address the following:
A statement of the “purpose and scope”.
Consideration and documentation of all precautions that must be observed whilst
performing the tests in order to avoid potential hazards.
Identification of any special tools or equipment required and evidence that the personnel
are competent to use such equipment.