Contract, cost-plus-
incentive-fee:
A cost reimbursement type of contract for construction of a turnkey
project where the supplier’s fee is linked to the actual costs in relation
to the estimated or the target cost so that there is an incentive for
the supplier to achieve cost reduction.
Contract documents:
A set of documents that conveys the contract between the buyer
and the supplier in such a way as to minimise misunderstanding. It
could include: The instrument of the contract – the actual document
signed by both parties. General conditions of contract. Special
conditions of contract. Specifications/terms of reference/drawings/
bills of quantities/timetables/schedules of rates/terms of delivery
etc., copies of any relevant meeting minutes or letters that have
been exchanged. Curricula vitae of staff selected to carry out the
activities. Specimen of bonds. See also Contract.
Contract fixed price:
Acontract that provides for a fixed price not subject to any adjustment
on account of cost increases that a supplier may experience in the
course of execution of the contract.
Contract, fixed price
with revision:
A variation of a fixed price type of contract which provides for the
upward or downward changes in prices of specified materials and/
or of labour costs.
Contract modification:
Any change in the provision of any one or more of the terms and
conditions of a contract, proposed by one party and carried out
with the agreement of the other party. Legally a modification in a
contract amounts to agreeing to a new contract unless the intended
modifications are provided for in the contract, e.g., plus/minus option
on quantities, lot sizes, etc. See also Buyer’s option and Supplier’s
option.
Contract period:
An arrangement for the supply of goods or services established for
a fixed period of time.
Contract scheduling:
A systems approach to help monitor contract implementation.
Particularly useful for contracts for large projects where different
activities have to be carried out in a sequence within a time frame
and where delay in the completion of one segment of a project is
likely to delay the execution of the whole project. See also Expedite
and Follow-up.
Contractor:
Aphrase often used for a company carrying out construction works.
Sometimes used in a more general way for all types of suppliers of
goods, works or services.