Table of Contents Table of Contents
Previous Page  429 / 536 Next Page
Information
Show Menu
Previous Page 429 / 536 Next Page
Page Background

415

CYIL 7 ȍ2016Ȏ

THIRD PARTY TO PICK UP THE BILL?…

Assenting Opinion reversing the burden of proof: “once it appears that there is third

party funding of an investor’s claims, the onus is cast on the claimant to disclose

relevant factors and to make case why security for costs orders should not be made.”

13

Also a dissent of Edward Nottingham concentrated on this issue, when in his view,

“the general concerns about third party funding and security for costs can and should

be addressed by the Administrative Council of ICSID in its rule-making capacity, if

there is a problem that needs to be dealt with.”

14

It is possible to identify an approach close to the reasoning of the tribunal in

Guaracachi America, Inc and Rurelec plc v. Bolivia

in

EuroGas Inc and Belmont Resources

Inc v. Slovak Republic

. The tribunal recalled that security for costs may only be granted

in exceptional circumstances, “for example where abuse or serious misconduct has

been evidenced,” and observed facts in

RSM Production Corporation v. Saint Lucia

as “rather exceptional since the claimant was not only impecunious and funded by

a third party, but also had a proven history of not complying with cost orders.”

15

Considering the claimant’s payment discipline and seeing third-party funding as an

increasingly common practice, which “do not necessarily constitute

per se

exceptional

circumstances” to grant security.

16

In

Ticaret Ltd. Sti v. Turkmenistan

the relationship between security for costs and

third party funding was highlighted by the tribunal. In its Order the tribunal stated

that, after the host State “indicated that it will be making an application for security

for costs”, it would be unclear what basis there would be for such application, “e.g.

claimants’ inability to pay respondent’s costs and/or the existence of a third-party

funder”.

17

Reviewing the cases described above, it is easy to conclude that there is no uniform

or prevailing trend towards the issue of security for costs. Although presence of a TPF

does not itself establish a sufficient reason

per se

to grant security, tribunals increasingly

recognise its significance while considering claimants’ financial dispositions. As

third party funding is increasingly used by large, solvent, companies to balance the

risks involving the commencement of investment arbitration, a concluded funding

agreement is not evidence that the claimant is impecunious.

18

13

RSM Production Corporation v. Saint Lucia

, ICSID Case No. ARB/12/10, Assenting Reasons of Gavan

Griffith (12 August 2014), paras 17-18.

14

RSM Production Corporation v. Saint Lucia

, ICSID Case No. ARB/12/10, Dissenting Opinion of

Edward Nottingham (12 August 2014), para 20.

15

EuroGas Inc. and Belmont Resources Inc. v. Slovak Republic, ICSID Case No. ARB/14/14

Procedural

Order No. 3 Decision on the Parties’ Request for Provisional Measures (21 June 2015), paras 121-122.

16

Ibid

., para 123.

17

Muhammet

Çap

& Sehil Inşaat Endustri ve Ticaret Ltd. Sti v. Turkmenistan

, ICSID Case No. ARB/12/6,

Procedural Order No. 3 (12 June 2015), para 10.

18

ICCA-Queen Mary Task Force on Third-Party Funding in International Arbitration,

Draft Report on

Security for Costs and Costs

(1 February 2016), p. 16.