Previous Page  54 / 72 Next Page
Information
Show Menu
Previous Page 54 / 72 Next Page
Page Background

DECEMBER • 2016

Construction

WORLD

52

Professional Services

C

While operational, large dewatering programmes must be

implemented to allow the miners to tunnel, blast and to ultimately

extract gold. With the closure of the mines and the turning off of

the dewatering pumps, water started accumulating in the old mine

workings, leaving deep shafts that provide direct access for water

and oxygen to underground rock surfaces.

Through natural oxidation of pyrite bearing rock strata, the

water that filters into these empty shafts via recharge and runoff

water is characterised by acidity, high metal content and high

salinity, and is known as Acid Mine Drainage (AMD).

Decant of AMD started in the West Rand in 2002. Similar

decant was anticipated in Central and Eastern Basins. It was

imperative that something be done to stop the AMD contaminating

the groundwater to a point where it is unsuitable for domestic or

other uses.

The Treatment Plant designed by AECOM for the Eastern Basins

is a High Density Sludge (HDS) Plant which is treating a maximum

of 110 Ml/day of AMD.

The scheme’s design followed the typical industry practice

as used for water/wastewater treatment works. Some of the

aspects of the detailed design were verified using state of the art

techniques, used to optimise the detail design, add value to the

engineering design and ensure cost savings for the client.

Some of the technology used on the project was tried and

tested systems which perhaps were lacking originality, but simply

due to the size of the project these are now the largest examples

in the world.

An improvement over the typical HDS process was the

enhanced sulphate removal system by providing additional

retention time in a mixed Gypsum Crystallisation tank.

On commencing with construction, an underwater camera

was lowered into the flooded mine shaft to ensure that there were

no blockages. A modified sonar was also lowered into the shaft

to give a wider field of view to reduce the risk of damage to the

abstraction pumps when they were lowered.

The mine shaft used as the AMD abstraction point had been in

disuse for some years and had suffered from lack of maintenance

and vandalism by illegal miners. Use was made of professional

mining rescue teams with the necessary equipment and

experience to remove debris and clear obstacles from the mine

shafts above the water line.

Constrained by a railway on one side and a wetland on the

other, the site was challenging. The plant was designed so that the

large thickener recycle pump station excavations (8 m deep from

natural ground level and requiring lateral support) were moved as

far out of the wetland as possible.

The excavations for the thickeners were still a cause of

considerable construction difficulties. The material being

excavated was a silty clay that was prone to shear failures.

Extreme care had to be taken during excavation.

A number of solutions were considered by the team including

drilling with casings and other forms of lateral support. The

decision was taken to use self-drilling anchors, which flush the

area with grout while drilling occurs, to enable the hole to stay

open while voids are grouted and stabilised in the same operation.

This solution was successfully executed and the lateral support

was successfully installed in the large thickener excavations.

Concern about the environment steered the project as a whole.

ACID MINE DRAINAGE PROJECT:

EASTERN BASIN TREATMENT PLANT

98% of the gold that has been mined in South

Africa has come from the Witwatersrand

goldfields. For more than a century, gold was the

most important export commodity, but over the

past 25-30 years gold production has suffered

a drastic decline. In 1970 South Africa was still

producing 1 000 tonnes of gold each year, two

thirds of world production; but by 2010 this had

dropped to just 192 tonnes, a mere 10% of

world production.

Project information

• Company entering: AECOM

• Client: Trans Caledon Tunnel Authority

• Start date: June 2014

• End date: August 2016

• Main contractor: CMC PG Mavundla JV

• Project manager: Trans Caledon Tunnel Authority

• Quantity surveyor: AECOM

• Consulting engineer: AECOM

• Subcontractor: Tecroveer

If the project did not stick rigidly to the programme

dates, the AMD in the mining void would rise to a point

that it would pollute natural aquifers and potentially

decant at surface.

Construction on the Eastern Basin AMD Site

occurred within the bounds of the Blesbokspruit, which

had previously been registered as a RAMSAR area of

natural importance. Detailed measures and processes

were put into place to ensure that construction

activities did not negatively impact the wetland.

Highly Commended