Previous Page  59 / 72 Next Page
Information
Show Menu
Previous Page 59 / 72 Next Page
Page Background

2 16

BEST

PR

O

JECTS

57

DECEMBER • 2016

of gantries and the transfer house sections to the top of Silo 20,

which include lifts in excess of 40 t, and commissioning at the live

power station. The project scope is large and complex, with the

main focus being a very tight deadline.

It is an interesting project in that the entire Silo 20 was not

demolished. Rather the base and bottom half from the hopper up

were incorporated into the new structure. Another engineering

design challenge has been to ensure that the plant, which was built

originally over 20 years ago, complies with all the latest regulations

and requirements, without changing any fundamentals such as

the layout. A significant challenge is that the coal feed to the fully

functioning power station cannot be interrupted at all, which is

why Eskom has phased the project, with a bypass conveyor as an

interim solution.

Silo 20 is 65 m high, which presents a challenge in terms of

heavy lifts due to the windy conditions at this time of year, as well

as significant safety risks to all individuals working at heights to

perform these difficult installations.

Another major challenge in terms of the sliding in particular is

that the concrete mix has to be precise, an area where Hatch’s site

engineers paid particular attention to.

Project information

• Company entering: Hatch

• Client: Eskom

• Project start date: May 2015

• Project end date: December 2016

• Main contractor: Rula/Stefanutti

Stocks Consortium

MAJUBA POWER STATION

SILO 20 RECOVERY PROJECT

In November 2014, an incident occurred at Majuba, during which

the wall of Silo 20 fractured, leading to the collapse of the upper

section of the silo. The conveyor transfer house and the coal

conveyor gantry sections that were supported by Silo 20 also

collapsed, resulting in damage to the head end of the overland

conveyors, take up structures and the tail ends of the over-silo

link conveyors.

The configuration of the coal plant relies on the distribution

of coal to the desired silo from the Transfer House located on

top of Silo 20. Due to the structural failure of Silo 20 and the

associated conveying infrastructure, no coal supply to any of

the silos was possible.

Hatch won a competitive tender to provide engineering services

for the permanent solution, consisting of a detailed civil and

structural design for the plant, as well as a basic design, for all

associated interfacing plant, including Bulk Material Handling

(BMH), Electrical, Control and Instrumentation (C&I) and Low

Pressure Services (LPS).

The scope of the permanent solution project includes Silo 20

reinstatement, strengthening of Silos 10 and 30 and all supporting

systems. During the design phase, the urgent timeframe resulted

in Hatch having to shave several weeks off the engineering

design schedule. To date the project has been a success.

Challenges going forward include conveyor construction, lifting

Majuba is a six-unit, coal-fired power station that

produces a total of 4 107 MW of electricity.

It comprises three dry-cooled units producing

657 MW each, and three wet-cooled units

producing 712 MW each. Construction started in

1983, with the first unit connected to the national

grid in 1996. The last unit was connected in 2001.