P & I Design Ltd.
Control Panel Specification
P & I REF.
PNL-##A2.SPC
SHT
9
OF
9
11.0
Delivery
The panel shall be adequately protected to prevent damage to the enclosure and its contents
during loading, transportation and off loading.
12.0
Documentation and Certification
12.1
Where the enclosure utilises custom built steelwork, the manufacturer shall be responsible
for preparing any drawings required, other than the panel cut-out/layout drawing supplied
by P & I Design, to enable the enclosure to be built.
P & I Design require 2 copies of any such drawings prior to manufacture.
12.2
The manufacturer shall provide certificates for all tests conducted on the panel under his
control.
12.3
The equipment supplied shall comply with and shall be constructed to allow operation and
maintenance in accordance with the following regulations:-
IEE Regulations (Current Edition)
Health and Safety at Work Act 1974