Background Image
Previous Page  14 / 60 Next Page
Information
Show Menu
Previous Page 14 / 60 Next Page
Page Background

12

MODERN MINING

March 2015

MINING News

In its report on the December quarter,

Aureus Mining Inc, listed on the TSX and

AIM, says that construction has continued

to progress on its New Liberty Gold Mine

(NLGM) in Liberia despite the challenges

of operating throughout the Ebola out-

break. The first gold pour at New Liberty is

expected by the end of May 2015.

Vast Resources to divest itself of its Zambian assets

New Liberty on target to pour first gold in May

All significant areas of civil works have

now been completed and handed over

to the structural steel, mechanical, plate

work and piping (SMPP) contractor for

steelworks and further commissioning.

The primary and secondary crushers and

ball mill are now fully installed and await-

ing power for directional testing with work

Mining equipment working in New Liberty’s Larjor pit. Although Aureus is undertaking the mining itself, the min-

ing fleet has been supplied and is being maintained by MonuRent (photo: Aureus Mining).

focusing on the completion of the con-

veyor systems.

According to Aureus, the Marvoe Creek

diversion and Kinjor and Larjor village

relocations were completed in mid-2014,

allowing the commencement of mining

operations in October 2014, with the first

blast of 25 000 tonnes of waste rock suc-

cessfully completed in January 2015.

A new updated mine plan aligned

to the current gold price environment

has been developed to further de-risk

the project. The plan increases opera-

tional flexibility through the creation of

two starter pits, providing increased face

length and stockpile management and

giving greater confidence that production

targets will be met.

Expected all-in sustaining cash costs are

reduced by 7 % to US$789/oz and the post-

tax project NPV of expected cash flows from

commencement of commercial production

increase to US$328 million. An additional

28 000 ounces of gold is expected to be

produced in the first year of production

through the mining of an additional starter

pit, which brings the total Year 1 target pro-

duction to 122 000 ounces of gold.

Although New Liberty is expected to

be producing gold by the end of May this

year, further plant optimisation and final

commissioning is only expected to occur

in June and July, leading to steady state

production at the end of July 2015.

AIM-listed Vast Resources plc (previously

African Consolidated Resources) reports

that – as part of the transition of its focus

from exploration to mining and to near

term cash generation – it has, subject to

due diligence, agreed to divest its non-

core Zambian assets.

It has agreed to sell its subsidiary,

African Consolidated Resources (Zambia)

Limited, and the company’s remaining

directly owned Zambian copper inter-

ests, which include its contract to acquire

the Kalengwa mine for US$1,1 million. It

has also entered into an earn-in arrange-

ment for the continued exploration of the

Nkombwa Hills project for rare earths and

phosphates under the operational man-

agement of a new earn-in partner.

Roy Pitchford, Chief Executive Officer,

commented: “Over recent months our

attention has turned toward high value

brownfield assets with the ability to

generate material cash flow in the near

term. With these criteria in mind, the

Baita Bihor polymetallic mine in Romania

and the Pickstone-Peerless gold project

in Zimbabwe have been prioritised for

accelerated development. Subject to

the conclusion of satisfactory due dili-

gence and the subsequent acquisition

of an interest in Baita Bihor, the Board is

targeting commercial production from

both Baita Bihor and Pickstone-Peerless

by H2 2015.

“With this strategy in mind, it has

become evident to us that success in

Zambia requires a considerable investment

by the company, not only in money but in

senior management time. It is our opinion

that, notwithstanding the potential of our

Zambian assets, the immediate resources

required to achieve a successful operation

in Zambia would be better utilised on min-

ing and short term cash generation in the

areas of our ongoing focus.

“I am therefore very pleased that we

have achieved, on the one hand, an out-

right sale and release from future liabilities

in relation to our Zambian copper assets

and, on the other hand, an earn-in agree-

ment on our Nkombwa Hill assets where

we retain a significant interest but with no

further investment required and no mate-

rial demands on management time.”