Potential Change Orders

With Owner Info - Summary Log, Grouped By Category

[JRCC]

Riverbend - Building B

J. Raymond Construction Corp

Project # 06-024

2307 W BROWARD BLVD

FT LAUDERDALE, FL 33312

Tel: (954) 583-0021 Fax: (954) 583-0160

Internal

PCCO

Number Description

COR No

PCCO No

Estimate

Is Closed

Amount

Reimbursable Change

003

Elevator Upgrades

002

5,887.00

AIA

A00111-1997 - 001

0

X

005

Plumbing - Misc Changes [Revisions to Plumbing Drawings through 8/1/07]

003

12,861.00

AIA

A00111-1997 - 001

12,861

X

006

Credit for Alternate Cooling Tower

010

)

(10,475.00

AIA

A00111-1997 - 002

)

(10,475

X

008

Credit for Alternate Granite @ Lobby

005

)

(10,345.00

AIA

A00111-1997 - 002

0

X

009

Credit Owner's Contingency

011

)

(27,235.00

AIA

A00111-1997 - 002

)

(27,235

X

013

Revised Mechanical / Fire Sprinkler - City Permit Comments

006

7,570.00

AIA

A00111-1997 - 003

7,570

X

014

Lobby Wall Finishes

001

111,452.00

AIA

A00111-1997 - 001

111,452

X

015

Revised Entrance Canopy Proposal

007

63,448.00

AIA

A00111-1997 - 004

196,728

X

017

Lobby Tenant Door Upgrade East Lobby - Frameless Stainless Steel

16,000.00

0

X

018

Lobby Tenant Door Upgrade - West Lobby

8,380.00

0

X

019

Door Changes / Added Fire Doors per City Permit Comments

012

30,325.00

AIA

A00111-1997 - 005

30,325

X

020

Generator / Revised Electrical Riser / Credit for MC Cable

004

90,714.00

AIA

A00111-1997 - 001

90,714

X

022

Domestic Water Service / Fire Service to Building [Invoiced Out Side of

Contract]

009

13,334.00

13,334

X

Prolog Manager

Printed on: 11/29/2010

PM_JRCC

Page 1

SAMPLE