ID
Task
Mode
Task Name
Duration Start
Finish
1
SHELL CONSTRUCTION
170 days 7/10/17 3/2/18
2
Foundations / Elevator Pits
3 wks
7/10/17 7/28/17
3
1st Elevated Deck ‐ Structural Frame
3 wks
7/31/17 8/18/17
4
1st Elevatated Deck ‐ FRP
2 wks
9/11/17 9/22/17
5
2nd Elevated Deck ‐ Structural Frame
3 wks
8/21/17 9/8/17
6
2nd Elevated Deck ‐ FRP
2 wks
10/2/17 10/13/17
7
3rd Elevated Deck ‐ Structural Frame
3 wks
9/11/17 9/29/17
8
3rd Elevated Deck ‐ FRP
2 wks
10/23/17 11/3/17
9
4th Elevated Deck ‐ Structural Frame
3 wks
10/2/17 10/20/17
10
4th Elevated Deck ‐ FRP
1.5 wks 11/13/17 11/22/17
11
Roof Joists and Deck
3 wks
10/23/17 11/10/17
12
Initial Roof Membrane
1 wk
11/13/17 11/17/17
13
Level 1 ‐ MEP Underground Rough
10 days 10/23/17 11/3/17
14
Level 1 ‐ Slab on Grade
7 days
11/6/17 11/14/17
15
Level 1 Core / Lobby
15 wks 11/15/17 2/27/18
16
Level 2 Core
10 wks 11/6/17 1/12/18
17
Level 3 Core
10 wks 11/20/17 1/26/18
18
Level 4 Core
10 wks 12/4/17 2/9/18
19
Level 5 Core
10 wks 12/18/17 2/23/18
20
Building Envelope
16 wks 11/13/17 3/2/18
21
22
Elevator Installation
8 wks
1/8/18 3/2/18
23
Stair Wells
6 wks
11/22/17 1/3/18
24
25
TENANT CONSTRUCTION
110 days 12/18/17 5/18/18
26
Level 1 ‐ Tenant Improvements
16 wks 12/27/17 4/17/18
27
Level 2 ‐ Tenant Improvements
16 wks 12/18/17 4/6/18
28
Level 3 ‐ Tenant Improvements
16 wks 1/1/18 4/20/18
29
Level 4 ‐ Tenant Improvements
16 wks 1/15/18 5/4/18
30
Level 5 ‐ Tenant Improvements
16 wks 1/29/18 5/18/18
Foundations / Elevator Pits
1st Elevated Deck - Structural Frame
1st Elevatated Deck - FRP
2nd Elevated Deck - Structural Frame
2nd Elevated Deck - FRP
3rd Elevated Deck - Structural Frame
3rd Elevated Deck - FRP
4th Elevated Deck - Structural Frame
4th Elevated Deck - FRP
Roof Joists and Deck
Initial Roof Membrane
Level 1 - MEP Underground Rough
Level 1 - Slab on Grade
Level 1 Core / Lobby
Level 2 Core
Level 3 Core
Level 4 Core
Level 5 Core
Building Envelope
Elevator Installation
Stair Wells
Level 1 - Tenant Improvements
Level 2 - Tenant Improvements
Level 3 - Tenant Improvements
Level 4 - Tenant Improvements
Level 5 - Tenant Improvem
2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 2
July
August
September October
November
December
January
February March
April
May
June
July
Task
Split
Milestone
Summary
Project Summary
ONIX GROUP
Clinical Research Building (Orlando, FL)
Preliminary Construction Schedule: 12/20/16
Page 1
Project: Preliminary Project Sch
Date: 12/20/16