ID

Task

Mode

Task Name

Duration Start

Finish

1

SHELL CONSTRUCTION

170 days 7/10/17 3/2/18

2

Foundations / Elevator Pits

3 wks

7/10/17 7/28/17

3

1st Elevated Deck ‐ Structural Frame

3 wks

7/31/17 8/18/17

4

1st Elevatated Deck ‐ FRP

2 wks

9/11/17 9/22/17

5

2nd Elevated Deck ‐ Structural Frame

3 wks

8/21/17 9/8/17

6

2nd Elevated Deck ‐ FRP

2 wks

10/2/17 10/13/17

7

3rd Elevated Deck ‐ Structural Frame

3 wks

9/11/17 9/29/17

8

3rd Elevated Deck ‐ FRP

2 wks

10/23/17 11/3/17

9

4th Elevated Deck ‐ Structural Frame

3 wks

10/2/17 10/20/17

10

4th Elevated Deck ‐ FRP

1.5 wks 11/13/17 11/22/17

11

Roof Joists and Deck

3 wks

10/23/17 11/10/17

12

Initial Roof Membrane

1 wk

11/13/17 11/17/17

13

Level 1 ‐ MEP Underground Rough

10 days 10/23/17 11/3/17

14

Level 1 ‐ Slab on Grade

7 days

11/6/17 11/14/17

15

Level 1 Core / Lobby

15 wks 11/15/17 2/27/18

16

Level 2 Core

10 wks 11/6/17 1/12/18

17

Level 3 Core

10 wks 11/20/17 1/26/18

18

Level 4 Core

10 wks 12/4/17 2/9/18

19

Level 5 Core

10 wks 12/18/17 2/23/18

20

Building Envelope

16 wks 11/13/17 3/2/18

21

22

Elevator Installation

8 wks

1/8/18 3/2/18

23

Stair Wells

6 wks

11/22/17 1/3/18

24

25

TENANT CONSTRUCTION

110 days 12/18/17 5/18/18

26

Level 1 ‐ Tenant Improvements

16 wks 12/27/17 4/17/18

27

Level 2 ‐ Tenant Improvements

16 wks 12/18/17 4/6/18

28

Level 3 ‐ Tenant Improvements

16 wks 1/1/18 4/20/18

29

Level 4 ‐ Tenant Improvements

16 wks 1/15/18 5/4/18

30

Level 5 ‐ Tenant Improvements

16 wks 1/29/18 5/18/18

Foundations / Elevator Pits

1st Elevated Deck - Structural Frame

1st Elevatated Deck - FRP

2nd Elevated Deck - Structural Frame

2nd Elevated Deck - FRP

3rd Elevated Deck - Structural Frame

3rd Elevated Deck - FRP

4th Elevated Deck - Structural Frame

4th Elevated Deck - FRP

Roof Joists and Deck

Initial Roof Membrane

Level 1 - MEP Underground Rough

Level 1 - Slab on Grade

Level 1 Core / Lobby

Level 2 Core

Level 3 Core

Level 4 Core

Level 5 Core

Building Envelope

Elevator Installation

Stair Wells

Level 1 - Tenant Improvements

Level 2 - Tenant Improvements

Level 3 - Tenant Improvements

Level 4 - Tenant Improvements

Level 5 - Tenant Improvem

2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 2

July

August

September October

November

December

January

February March

April

May

June

July

Task

Split

Milestone

Summary

Project Summary

ONIX GROUP

Clinical Research Building (Orlando, FL)

Preliminary Construction Schedule: 12/20/16

Page 1

Project: Preliminary Project Sch

Date: 12/20/16