Previous Page  184 / 736 Next Page
Information
Show Menu
Previous Page 184 / 736 Next Page
Page Background

culars were obtained. They were delivered early

in

1966.

At the end of

1966

the plaintiffs were

still waiting for a list of documents from F which

they only received after they had taken out a

summons for judgment in default of delivery of

the list. In

January 1967

discovery was sought

by the defendant but not offered until

November

of that year; in

January 1968

after the 3 Court

of Appeal decisions in Alien v. Sir Alfred

MeAlpine & Sons Ltd. (1968) 2 WLR 366; the

defendant's solicitors took out a summons to dis

miss the action for want of prosecution. Master

Diamond refused to dismiss the action and

ordered it to be tried by an official referee; Cooke,

J. on appeal reversed the order on the grounds of

the plaintiffs' delay since

January 1967;

his view

was that a fair trial could not be had after so

great a delay and he refused leave to appeal. On

appeal by the plaintiffs the Court of Appeal had

before it an affidavit by their solicitor explaining

part of the delay since

January 1967.

Lord Denning M. R. said that the real ques

tion was how the plaintiffs 8 or 9 months delay

since January, 1967 was such that their action

should now be dismissed for want of prosecution.

The delays were deplorable on both sides. But the

outstanding point in the present case was that

F himself

by his solicitors

had largely contributed

to the delays and brought them about by the pro

cedure adopted, and now at the last moment

sought to escape trial by saying that in the last

few months the plaintiffs had delayed. Though

there had been such delay, the prime cause was

the defendant's tactics. In those circumstances it

would not be just to dismiss a claim against him

for work done on his own house. The appeal

should be allowed and the matter ordered to be

tried before the official referee and disposed of

quickly and finally.

Diplock, L. J. said that it

was a borderline case and on an oral contract

and there was a risk that a fair trial of the issue

would no longer be possible. The position had

arisen in January 1967, already 8 years after the

events constituting the cause of the action. There

had not been mere non-activity on the part of the

defendant in this case.

He or his solicitors had

adopted procedures which positively invited de

lay;

and the plaintiffs' tardiness in the latter

stages was not sufficient to justify their action

now being dismissed for want of prosecution.

Sachs, L. J., also concurring, said that he would

hesitate long before making an order which

would result in the plaintiffs foregoing all pay

ment for work and would ensure that someone,

prima facie the defendant, got that benefit for his

own house, without personally making any pay­

ment either to the builders or anyone else. The

defendant by the conduct of the defence had dis

played symptoms of making the case so burden

some as not to be worth pursuing. It would be

contrary to the justice of the case to strike out

the plaintiff's claim finally. Appeal allowed.

No

order for costs, the solicitors on both sides to

understand that they should pay their own costs.

(George A. Poole Ltd. v. Forrest. Vol. 112.

S.J. 355).

House Purchase-Building Contract

By contract in writing dated November 21st

1958 a firm of Building Contractors agreed to build

a dwelling house for the plaintiff and to "build

and complete in a workmanlike manner and ac

cording with the specification hereto annexed".

On February 3rd, 1960 the local authority issued

a certificate to the effect that the certifier had

examined the dwelling house and "that the same

has been constructed to the best of (his) know

ledge and in accordance with the (deposited)

plans and the by laws of the Council and is fit

for human habitation". Certain defects developed

later. These were caused, so the Court found, by

failure to carry the foundations of the house on

the North-West side to a sufficient depth. In

action for damages the defendants contended,

among other contentions, that the certificate was

made conclusive evidence of the completion of

the house in accordance with the Council and

that thereafter no complaint could be main

tained by the plaintiff.

Held the plaintiff was entitled to a, damages

because :—

1. the relevant clause of the contract did not

bar the plaintiff's claims since the certificate

thereunder was conclusive only that the house

was completed and was not conclusive against

complaints, such as complaints, defects in con

struction, otherwise open to the plaintiff.

2. There was some ambiguity in the clause of

the contract whether having regard to the con

tract in the specification and particularly the

following—"and to (the local authority) satis

faction" the approval of the local authority pro

vided an effective answer to the plaintiff's claim

for alleged breach of an obligation to be fulfilled

in a workmanlike manner; in view of the ambi

guity the primary obligation "in a workmanlike

manner" was not so limited, that defendents

obligation under the contract remained an

obligation to build in a workmanlike manner a