Table of Contents Table of Contents
Previous Page  400 / 532 Next Page
Information
Show Menu
Previous Page 400 / 532 Next Page
Page Background

384

ZUZANA JAHODNÍKOVÁ

MILOŠ OLÍK

CYIL 5 ȍ2014Ȏ

the ICSID sought to decline its jurisdiction. The Court, however, looked at the

nature of the claims and decided that there is a need to also consider the BIT breach

since “contractual claims arising out of the Contract do not have the same cause of

action as the Treaty claims”.

82

The Tribunal went on to rule that, when the conduct

of the State results in actions which cause a breach of contract and, at the same time,

constitutes a violation of the Treaty, the Tribunal both would be appropriate for and

would accept the jurisdiction, in spite of the Contract’s jurisdiction clause.

Choosing the route of avoiding the danger of parallel proceedings through the

usage of fork-in-road clauses seems like a suitable way to forestall the commencement

of several proceedings. In spite of the fact that this could be a straightforward approach

setting the conditions of investment litigation prior to a dispute, one cannot omit

the fact that certain problems arise when the exercise of domestic procedural rights is

ambiguous. This could make it rather difficult to pass a judgment on whether these

actions are triggering the applicability of the fork-in-road clause. As some authors

pertinently pointed out, an approach which would narrow the application of these

clauses to every action of an investor undertaken within the national legal order

would lead to a situation where “guarantees of effective domestic remedies (would be)

traps designed to lure an investor into domestic proceedings with the consequence that

the door to international arbitration will be closed forever no matter what the outcome

of the domestic proceedings may be”.

83

However, given the complexity of these clauses

and their limitations, in practice, they have had very little application so far. As one

commentator said, arbitral tribunals have demonstrated a tendency to deprive these

clauses of their genuine meaning by never applying them in favour of a state.

84

4.5 Parallel Litigation and the Denial of Justice

Indeed, the position of defying arbitration in conjunction with an intercurrent

process aimed at ceasing foreign adjudication constitute a basis for novel claims

brought about by investors. This could be seen in a scenario where a State’s court acts

in collusion or conspiracy with the State’s executive to obstruct an investor’s pursuit

of arbitration. Subsequently, in this case, it too has committed a denial of justice

and a breach of internationally accepted principles of arbitration law, for which the

State is responsible.

85

However, this prohibitive conduct could perhaps under some

circumstances not pass unnoticed and without any consequence.

but rejected the jurisdiction to rule on the contractual claims. The Tribunal held that “it is a claimant’s

prerogative to formulate the claims that it is asking the judges to resolve”

and that the alleged claims

have to be assessed in the further stages of the proceedings.

SGS v. Pakistan

, Decision of the Tribunal

on Objections to Jurisdiction, paras. 89-90.

82

Toto Costruzioni Generali S.p.A. v. Republic of Lebanon, supra

note 80, Decision on Jurisdiction,

11 September 2009, para. 211, p. 61.

83

Ch. Schreuer, “Travelling the BIT Route.”,

supra

note 71, p. 249.

84

P. Muchlinski, F. Ortino, Ch. Schreuer,

supra

note 58, p. 1027.

85

R. Garnett,

supra

note 26, p. 488 with reference to the

Saipem SpA v Bangladesh

ICSID case

No. ARB/05/7, Award of 30 June 2009 para. 147.