Previous Page  35 / 64 Next Page
Information
Show Menu
Previous Page 35 / 64 Next Page
Page Background

33

CONSTRUCTION WORLD

SEPTEMBER

2016

operations and traffic management were

carried out in strict accordance with the

Tsogo approved hoarding permit and traffic

management plan, thereby enhancing a

healthy relationship with the city.

With space being at such a premium,

it was imperative that the two tower cranes

were carefully positioned and ready to

operate immediately. The first crane is

supported by a base that is cast inside the

structure and the second by ballasts outside

of the building.

Meanwhile, the laydown area in the base-

ment provides very limited space for storing

essential building materials. The bulk of the

building requirements need to be stored off

site and their timeous delivery to the site

is planned on a just-in-time basis to avoid

disrupting the construction programme.

“Logistics of supply is critical on this

project. We have to plan very carefully and,

often, deliveries to site have to be done

in the evening when traffic in the city has

started to subside. This has allowed for an

uninterrupted start by the various teams the

following morning,” he says.

A congested site

Adding to these complexities is the number

of subcontractors interacting with the

main contractor on this congested site.

In June, Murray & Roberts Western Cape

was interacting with just under 40 sub-con-

tractors as work continued apace on the

specialised trades.

By the time the project peaks early next

year, the site is expected to host about 500

workers, adding a new level of complexity to

the project.

However, the biggest challenge on this

project was the large transfer slab at the fifth

level of the structure that marks the end of

the podium work and the start of the main

tower that houses the hotel.

Cement pours

Pouring this 1,1 metre thick slab above

the five podium levels required extensive

HOTSPOT

The old heritage building will be integrated into the hall of the new structure.

Once the transfer slab was successfully completed, the tower section started climbed quickly, with work

“Logistics of supply is critical

on this project. We have to

plan very carefully and, often,

deliveries to site have to be

done in the evening when

traffic in the city has started

to subside. This has allowed

for an uninterrupted start

by the various teams the

following morning.”

Subcontractors start with the installation of the services components of the structure and then install

the dry-walling, ceilings, doors, tiling and skirting.