Previous Page  36 / 64 Next Page
Information
Show Menu
Previous Page 36 / 64 Next Page
Page Background

34

CONSTRUCTION WORLD

SEPTEMBER

2016

PROJECT PROFILE

RIGHT:

The scaffolding for the external works had to be carefully designed to accommodate the different

trades involved in the façade that comprises different materials of different shapes and sizes.

BELOW:

The tower cranes had to be positioned carefully on the very congested site.

planning with the help of structural engi-

neer EKCON and principal agent, AECOM.

Danie Jurgens, engineer for Murray &

Roberts Western Cape, says an intricate

back-propping system had to be designed

and planned from the fifth level all the way

down to the basements to support the

transfer slab. The smallest pour was

320 m

3

and the largest 400 m

3

.

Jurgens says that in line with the

larger Murray Roberts Group’s STOP.THINK.

ACT 24/7 campaign no one was allowed

access in and around the site while the

concrete pours were under way.

The slab was undertaken in six individual

pours and the concrete pumped 42 m from

Bree and Buitengracht Streets in the early

hours of the morning to avoid peak hour

traffic in the CBD. About 2 000 m

3

of concrete

was cast, commencing on 3 February and

ending on 8 March 2016.

Complicating the process was the

intricate drainage system that had to be

cast inside the slab, as well as its extensive

reinforcing steel design.

To accommodate this, two 550 mm thick

concrete layers were poured on top of each

other with a five day curing period required

between layers. The surface of the first cast

was primed for the next pour by receiving a

thin layer of concrete with a retarding agent

and then sprayed with a jet of water.

External façade

Morilly says the external façade of the

building is also a complex undertaking. It

comprises different materials with a variety

of shapes and sizes. These include bricks,

windows and imported marble tiles, while

close consideration also had to be given to

the design of the scaffolding to accommo-

date the various tradesmen right from the

outset to avoid cost overruns.

A very interesting aspect of the build is

the merger of the new structure with the old

Tothills Building.

“This heritage building is being incor-

porated into the front of house of the new

structure and we have been tasked with

restoring it to its original state, overhauling

the roof, ceilings, walls and floors. We are

working closely with the structural engineers

and have already undertaken extensive tests

to validate the structural integrity of the

building,” Morilly says.

Work on the project commenced in

the rainy seasons in the Western Cape and

Murray & Roberts Western Cape and one year

into construction the company is on track for

the contract completion date.

It becomes very apparent that this will

be yet another successful project completed

by Murray & Roberts Western Cape in the

leading tourist destination in the country.