Background Image
Previous Page  11 / 52 Next Page
Information
Show Menu
Previous Page 11 / 52 Next Page
Page Background

February 2015

MODERN MINING

9

MINING News

Premier African Minerals Limited has provided

details of the Implementation Study report it

has prepared in regard to the open-pit start

up strategy for its RHA tungsten project in

Zimbabwe. Premier is the operator of the proj-

ect and holds a 49 % interest.

Highlights of the report include a reduction

in pre-production capital to US$4,15 million

and in operating costs to US$89,1/mtu (metric

ton unit). The pre-tax NPV (at a discount rate of

10%) is estimated at US$5,4million, the pre-tax

IRR at 161 % and the payback fromfirst produc-

tion at 10 months.

“The Implementation Study confirms

our strategy for RHA and supports our con-

clusions that the open pit is projected to

generate sufficient surplus cash to allow

both commencement of repayment of loans

made to RHA by Premier, and to finance the

build of the underground operations,” com-

ments George Roach, Premier’s CEO. “Most

encouraging is the projected operating cost

of US$89,1 per mtu WO

3

.”

RHA will target processing of 8 000 tonnes

of run of mine ore per month at a diluted grade

of 10,24 kg/t to produce, on average, 92 tons

of concentrate at 63 %WO

3

per month over a

22-month period.

The definitive estimate is a culmination

of work performed by Peacocke Simpson &

Associates, Appropriate Process Technologies

(APT), CAE Mining Africa, Senet, Blonton

Management Consultants, Ground Water

Development Consultants, Constant Chuma

Consulting and Bumira Environmental

Consultants and is considered suitable as

the control budget estimate for the execu-

tion phase (-5 % to +15 %).

The financial model incorporates firm

quotations for 80 % of the pre-production

capital estimate including fabrication and

installation of the process plant, earth-

works and civil works, a road upgrade,

the mining contract, as well as the pro-

curement and construction management

contract.

As we reported in last month’s issue,

Premier recently placed an order for

the project’s process plant. The plant is

designed to meet a throughput of 16 t/h

or 8 000 tonnes per month and achieve a

wolframite recovery of 82,8 %. The stated

production rate excludes any consideration

of a pre-concentration circuit which, if

implemented in future, could increase the

plant throughput fivefold at a 20 % recov-

ery loss as determined in the metallurgical

test work announced in September 2014.

The modular plant will be built in

Johannesburg by Appropriate Process

Technologies (APT). The modules will be

containerised and trucked to site where it

is expected that the process plant will be

fully commissioned by mid-2015.

The RHA project is located in Mata­

beleland North province, about 20 km

south-east of Hwange and 270 km north

of Bulawayo, the provincial capital.

Pre-production capex for tungsten

project in Zimbabwe reduced

The RHA project layout showing pit and waste dumps.