Background Image
Previous Page  25 / 52 Next Page
Information
Show Menu
Previous Page 25 / 52 Next Page
Page Background

GOLD

February 2015

MODERN MINING

23

Dewatering of the Nkran pit commenced in December 2014 and is expected to take up to ten

months to complete.

Workers assembled for

a safety briefing. As of

mid-January, there had

been no lost time accidents

on site with 231 days

of construction activity

and 348 330 man-hours

completed on the project.

of mine is expected to be 4,7:1 (waste to ore).

Nkran will be the source of 80 % of the ore with

the balance coming from four satellite deposits.

The mining contract for the pre-stripping

of the Nkran pit and the first year of opera-

tions was awarded in November 2014 to PW

Ghana Ltd (PW), a subsidiary of PW Mining

International Ltd of Accra, Ghana. PW mobil-

ised to site during November and December

2014 and has commenced the first stages of

pre-stripping. The process by which PW Ghana

was selected was very rigorous and began in

May last year when Asanko invited 19 mining

contractors to tender. This led to a short-list of

seven being compiled. The short-listed com-

panies were invited to submit more detailed

tenders in July last year, with four of these ten-

ders then being selected for detailed technical

and commercial review.

Dewatering of the Nkran pit – which was

previously mined and closed in 2002 due to the

then low gold price – began in the December

2014 quarter and is expected to take up to

ten months to complete. As at the end of the

December, the water level in the pit had already

reduced by approximately 2 m. The dewater-

ing will continue throughout the year and will

occur in parallel with the pre-stripping opera-

tion and is proceeding on schedule.

In terms of the staffing of the new mine,

Asanko Gold promoted Charles Amoah to

General Manager – Asanko Gold Mine in

December 2014 following the resignation

of Jonathan Ebo Collins. Amoah was previ-

ously Manager – Processing. He is a Ghanaian

national and a metallurgist with over 22 years

of experience. He has held a number of senior

management positions in the Ghanaian gold

mining industry, including General Manager of

PMI Gold Corporation’s Obotan project, as well

as Acting GM and Metallurgical Manager of the

Damang mine, which is 90 % owned by Gold

Fields. He holds a Certificate in Management

Development and a Masters degree in mineral

processing.

Asanko has now filled the majority of the

key operating positions at the Asanko Gold

Mine in readiness for the commencement of

ore mining operations and plant commission-

ing later this year.

Photos courtesy of Asanko Gold Inc