Background Image
Table of Contents Table of Contents
Previous Page  71 / 76 Next Page
Information
Show Menu
Previous Page 71 / 76 Next Page
Page Background www.read-tpi.com

March 2015 Tube Products International

69

Cortez Subsea Ltd

– UK

info@cortezsubsea.com www.cortezsubsea.com

The linear separation between the Zap-Lok press

and the tensioner has a direct effect on the lay

rate of the system.

A longer back deck area and a greater separation

between the Zap-Lok press and the tensioner will

mean that there can be several connected joints

between the Zap-Lok press and the tensioner,

therefore allowing some of the Zapoxy curing

time period to be brought offline, and the lay rate

increased.

The standard MPS stinger has been designed

to accommodate the largest anticipated loads,

but is adjustable in length such that it can be

shortened if required, depending on product and

water depth. The abandonment and recovery

winch is used in the same way as for traditional

pipelay methods, and is used for controlled

laydown and recovery of pipe.

The MPS system comes with its own electrical generators,

hydraulic HPUs and compressed air supplies to run the

system independently of the host vessel.

Installation and removal

“The MPS has been designed using similar sized structural

components, with similar types of bolted connections. All

the component parts have been design to be road or sea

transportable and fit within standard freight dimensions,”

explained Mr Cowie.

“The assembly of the component parts has also been

considered and the number of connections to be made has

been minimised.

“All structural foundations are based on similar sized beams,

meaning that the sea-fastening design is standardised, and

the overall dimensions of the foundations are designed such

that they span the required number of ‘hard points’ on a

typical deck to achieve the required values.”

Cortez Subsea says that individual component items, eg

pipe storage racks, can be assembled on the quayside prior

to the host vessel arrival and then lifted on as assembled

units. Larger items such as the Zap-Lok press, tensioner(s)

and A&R winches are bolted down onto bespoke bases that

form part of the MPS firing line foundation.

For demobilisation, the process is reversed with the focus on

getting the vessel off hire and available for other work. The

major items are stripped back to their component parts for

storage or shipment.

“What makes this unique is that the mechanical interface

joint is considerably quicker than the reeling process, which

involves pre-welding on shore,” added Mr Cowie. “It’s also

a safer option as there is no welding carried out offshore, so

fewer personnel are required on board. You also have better

control over the pipe’s alignment dimensions with this system

as it is cold-worked, and moreover since it is essentially a

manufactured joint.

“Most subsea development costs are increasing, which can

jeopardise future development or replacement projects. By

having the equipment needed for the pipelaying task designed

to be installed and operated from a vessel of opportunity

rather than hiring a specialist pipelay ship, the savings to

an operator are eye-catching and marginal subsea projects

may be able to achieve the required financial targets to gain

sanction.

“We can do the engineering analysis, carry out the work and

then allow the contractor to tie the pipeline in and complete

the commissioning. All you need is a DP2 vessel around 100m

long.

“Three of the major international operators and numerous

independents have approved the use of Zap-Lok for global

subsea operations in the past two years. Operators need to

make tiebacks and completions cheaper in the North Sea, and

using Zap-Lok is a great solution. These organisations see

the obvious advantages of the Zap-Lok technology. We are

now progressing towards fabrication and trials of the first of

the MPS units for operations. This is a significant step in the

development of our company towards advancing technology

and maximising value for the subsea market.”

Zap-Lok pipe connection system