THE UK OFFSHORE OIL AND GAS FABRICATORS DIRECTORY
2016
page 100
Projects and Markets
(continued)
Dudgeon
– Offshore Wind Substation Topsides and Jacket
Client:
Statoil UK
Period:
2015 to 2016 (under construction)
Contract:
Engineering, procurement and
construction (EPC)
Structure:
1,800 tonne high voltage electrical
substation topsides. 1,500 tonne jacket
substructure with suction piles
Golden Eagle
– Living Quarters, Bridge and Flare Modules
Client:
Nexen Petroleum UK Ltd
Period:
2011 to 2014
Contract:
Engineering, procurement and
construction (EPC)
Structure:
140-man, 2,000 tonne living quarters,
550 tonne bridge, 220 tonne flare
Katy
– Minimal Facilities Platform
Client:
ConocoPhillips UK
Period:
2012
Contract:
EPC
Structure:
Jacket substructure, piles and topside
Thorton Bank
– Offshore Wind Substation Jacket
Client:
Smulders - Belgium
Period:
2011
Contract:
Build only and deliver
Structure:
900 tonne offshore substation jacket
substructure