Previous Page  55 / 84 Next Page
Information
Show Menu
Previous Page 55 / 84 Next Page
Page Background

January 2017

MODERN MINING

53

Top projects

GOLD

Layout of the Esaase mining

operation.

handle 4 000 tonnes per day of mate-

rial and our crushing capability now

comfortably exceeds mill capacity.”

With Phase 1 beating its targets and

generating revenue, Asanko Gold was

able to announce in early November

that it would proceed with the Phase

2A expansion, which has an estimated

capital cost of circa US$125 million.

Phase 2A envisions the start-up

of mining operations at Esaase, the

construction of a 27 km overland con-

veyor to link Esaase and the Obotan

(Nkran) facilities and the expansion

of the existing Phase 1 processing

plant at Obotan from 3,6 Mt/a to

5 Mt/a to produce approximately

300 000 ounces of gold in 2018. The

upgraded plant will process a blend

of approximately 2 Mt/a of ore from Esaase and

3 Mt/a of ore from the Nkran pit and surround-

ing satellite deposits.

Looking at the Phase 2A scope in more

detail, Truter says that the plant upgrade –

which is scheduled for commissioning in Q1

2018 – requires only relatively minor capital

works. “We’re going to be increasing the capac-

ity of the mill discharge pumps, changing the

internals of the existing cyclone pack, adding

two Knelson gravity gold concentrators and

installing an additional Gekko intensive leach

reactor,” he elaborates. “We will also increase

gold room capacity and the capacity of the tail-

ings pumping system.

“At Esaase, where we will eventually have

three pits, we will first establish the South

pit, with a view to start mining operations

in Q2 2018. The other pits are the Main pit,

which will go down to approximately 400 m

and which hosts the bulk of the resource, and

the small North pit. As at Nkran, the mining

will be a standard truck-and-shovel operation

undertaken by a contract miner, with around

14 Cat 777 trucks – or equivalents – being

deployed initially. Infrastructure at Esaase

will include primary and secondary

crushing facilities.”

The biggest single component of

Phase 2A will be the overland con-

veyor which, at just over 27 km long,

will certainly rank as the longest

single flight conveyor in Africa and

possibly in the world. Although it tra-

verses largely flat terrain, there will

be 10 public road crossings, 27 pedes-

trian crossings and two haul road

crossings. It will feature HDPE idlers

for reduced noise and friction and is

designed to reduce spillage. The system will be

equipped with an ST2400 belt with a width of

800 mm – with a total mass of 1 305 tonnes –

and have an installed power of 2 800 kW.

Says Truter: “The conveyor will be able to

transport up to 1 200 t/h of ore which is suffi-

cient for Phases 2A and B although only 680 t/h

will be required in Phase 2A. We anticipate

commissioning in Q2 2018.”

DRA has been appointed as the EPCM

contractor for Phase 2A while the FEED con-

tract for the conveyor has been awarded to

ELB Engineering, which recently completed

the nearly 27 km long, 2 800 t/h Impumelelo

overland conveyor for Sasol Mining in

South Africa.

Based on present planning, implementa-

tion of Phase 2B – estimated to cost between

US$210 and US$220 million – will follow

hard on the heels on Phase 2A. This phase will

further expand the Obotan processing facility

with the construction of an additional 5 Mt/a

CIL circuit for a total processing capacity of

10 Mt/a (3 Mt/a from Nkran and its satellite

pits and 7 Mt/a from Esaase).

“An interesting point is that it was originally

Asanko Gold Mine – a thoroughly Ghanaian operation

Asanko Gold Mine currently employs approximately 1 700 people (including contrac-

tors), the vast majority of them (97 %) being Ghanaian nationals, with 44 % of them

coming from local communities. Asanko Gold in Ghana is headed by MD Joe Zvaipa –

who is a Zimbabwean – with Charles Amoah, previously the Met Manager (and acting

GM) of Gold Fields’ Damang Mine, as the General Manager.

Says Hugo Truter: “The skills base in Ghana, developed in over 100 years of com-

mercial gold mining, is such that we have little need to bring in expatriates. We do

provide some high level support to the mine from our office in Johannesburg but

Asanko Gold Mine is essentially an operation managed and manned by Ghanaians.”