Previous Page  61 / 84 Next Page
Information
Show Menu
Previous Page 61 / 84 Next Page
Page Background

January 2017

MODERN MINING

59

Top projects

Acting Mining Manager

Mario Cloete on site at

Gamsberg.

as a substantial amount of productive capac-

ity has been taken out of the market over the

past couple of years and has not been replaced.

“We’ll be the first new mine to start-up in what

is increasingly a market in deficit,” she says.

“The zinc price will obviously incentivise oth-

ers to bring on line new mines but at this stage

we’re way ahead of everyone else.”

One spin-off of the price plunge in early

2016 was that it motivated VZI to look at ways

of cutting Gamsberg’s capital budget. “We were

originally planning to owner mine at Gamsberg

but have now decided to use a mining contrac-

tor and this, of course, is a less capital intensive

approach,” says Naidoo. “We’ve also renegoti-

ated various contracts and re-engineered the

project to deliver substantial savings. All told,

we’ve reduced the capex by US$200 million –

which is an amazing achievement.”

Updating on the current status of the project,

Kumar – who used to be the GM at Skorpion –

says the ground-breaking ceremony was held

in July 2015 and that there are now around 300

workers on site, with this figure expected to

peak at 1 500 at the height of construction.

“Gamsberg is an inselberg that extends

about 220 m above the surrounding ‘flats’,” he

says. “We will be mining on top of the insel-

berg, so we’ve had to build roads to access the

mining area. We appointed a local Northern

Cape contractor, Roux Mining, to carry out

this work and to establish the starter pit and

they are making very good progress. Roux is

what we call the ‘pre-start contractor’ but we

have now appointed our bulk mining contrac-

tor, Aveng Moolmans, who will soon mobilise

to site. There’s a huge amount of pre-stripping

required to expose the orebody – close to 70 Mt

– so we will only start producing ore in the

middle of 2018. Although most of this pre-

stripping will be the responsibility of the bulk

mining contractor, Roux has made a start on it

and 12 Mt has been moved already.”

According to Kumar, the mining operation

at Gamsberg will be a conventional load-and-

haul exercise. “We have asked the contractor

to use the latest technologies in drilling but

other than this there is nothing unusual about

the approach being adopted. The strip ratio in

Phase 1 is about 7 to 1 so to achieve our targeted

ore production we’ll be moving over 30 Mt/a.

The explosives supply has been contracted out

to BME, who have been performing that func-

tion since 2015 when work first started on site.”

Moving to the process plant, Kumar

describes the flowsheet as “conventional with

some tweaks” and says it will include primary

crushing, milling (via SAG and ball mills),

flotation and dewatering. “We have three stages

of flotation, the first to take out carbon, the sec-

ond to remove the lead and the third for zinc,

with the final product being a 48 to 52 % zinc

concentrate,” he notes. He adds that the tail-

ings facility will be constructed to the highest

standards and will be HDPE lined.

The EPCM contractor for the processing

facility (and related infrastructure including the

power and water plants) is ELB Engineering,

who will be using – for the first time in a zinc

application – the new staged flotation reac-

tor (SFR) technology of Canada’s Woodgrove

Technologies in the plant. Benefits of the tech-

nology over conventional mechanical cells

reportedly include a much more compact foot-

print, reduced power and air requirements, less

instrumentation and reduced wear and mainte-

nance costs due to lower impeller tip speeds.

As regards the power required, VZI has con-

cluded an agreement with Eskom to supply

40 MW. The bulk water will be sourced from

the Orange River, just 33 km to the north of the

site. BMM already draws around 13 Mℓ a day

from the Orange for its current operations and

the new project will essentially double up on

this. Additional housing will also be needed

in the town of Aggeneys as the Gamsberg proj-

ect will generate over 500 new permanent jobs

once in full production.

While Gamsberg, like any big mining project,

has its share of technical challenges, perhaps

the biggest challenge of all is its location in the

arid Northern Cape in an area that has been

identified as a biodiversity hotspot. Explains

Naidoo: “Gamsberg lies in the Succulent Karoo

Biome – one of only four hotspots in South

Africa – which is home to 6 000 plant spe-

cies, and it also forms part of the Bushmanland

ZINC

“The zinc price

will obviously

incentivise others

to bring on line

newmines but at

this stage we’re

way ahead of

everyone else.”