Previous Page  8 / 84 Next Page
Information
Show Menu
Previous Page 8 / 84 Next Page
Page Background

6

MODERN MINING

January 2017

MINING News

AIM-listed Hummingbird Resources has

appointed African Mining Services (AMS), a

subsidiary of ASX-listed Ausdrill Limited, as

its mining contractor at the Yanfolila gold

project in Mali, where mine construction is

currently underway ahead of the first gold

pour, expected to occur in late 2017.

Comments Dan Betts, CEO of Hum­

mingbird Resources: “Appointing AMS as

our mining contractor is another major

milestone for Hummingbird and rep-

resents the single largest contract the

company will award. AMS has an excellent

reputation for high quality work with an

exemplary health and safety record. The

team also boasts over 25 years’ experience

operating in West Africa. I am delighted to

embark on this partnership with AMS as

we look forward to the commencement of

mining at Yanfolila.”

Hummingbird has appointed AMS

for an initial three-year period with an

option for the company to extend the

contract by a further year of mining. The

total value of the contract is expected to

be approximately US$112 million over

three years. The pricing represents a circa

5 % improvement for the company, as

well as increased flexibility and transpar-

ency, when compared to Hummingbird’s

Definitive Feasibility Study (DFS), released

in February 2016.

AMS anticipates incurring capital

expenditure of approximately US$38 mil-

Hummingbird appoints mining contractor for Yanfolila

lion for the acquisition of new equipment

and says it will employ around 450 person-

nel (the majority of whom will be local) for

this contract.

Mining operations at Yanfolila will be

carried out using conventional drill-and-

blast and load-and-haul mining methods

from two deposits initially. Mining is due

to commence in Q3 2017 with the first gold

pour due by the end of Q4 2017.

Yanfolila is Hummingbird’s most

advanced asset. Some 132 000 oz gold is

targeted for its first full year of production,

which would deliver around US$70 million

of free cash flow at a US$1 250/oz gold

A recent view of the Yanfolila site showing the start of construction operations. The first concrete pour

was in October (photo: Hummingbird).

Articulated haulers and excavators at work at Yanfolila (photo: Hummingbird).

price. On its initial eight-year mine life,

Yanfolila has an IRR of 60 % and an NPV of

US$162 million at a US$1 250 gold price,

making it – says Hummingbird – one of the

highest margin undeveloped gold projects

in Africa.

All in sustaining cash costs of US$695

per ounce place it in the lowest quartile

of African producers, and well placed to

operate profitably in a lower gold price

environment. Yanfolila is fully funded to

production and commitments to date rep-

resent nearly 30 % of the project capex.

According to Hummingbird, the project is

currently on budget and schedule.

There is also considerable upside at

Yanfolila, with over 1 Moz of gold outside

of the mine plan but within the permit as

well as the Gonka deposit (5 km south of

the Yanfolila plant), which – based on the

desktop study undertaken by DRA Projects

(as announced in February 2016) – can add

a further US$24 million to the NPV alone.

Yanfolila is now reported to be a hive of

activity with good progress beingmade on

the ground. A few short months ago, only

earthworks had been completed and now,

with civil works underway, the project is on

track for steelwork to begin in the coming

weeks.

Hummingbird says that in December

its executive team visited the factories

in Europe which are presently construct-

ing the ball mill and gearing and that its

members were impressed by the excellent

progress beingmade across all areas of this

critical aspect of the plant development.