Previous Page  9 / 84 Next Page
Information
Show Menu
Previous Page 9 / 84 Next Page
Page Background

January 2017

MODERN MINING

7

MINING News

Pan African Resources, listed on the

JSE and AIM, announced in December

positive results from the independent

Definitive Feasibility Study (DFS) for its

Elikhulu tailings project. As a consequence,

the company’s board of directors has

approved the construction of the project,

subject to finalisation of the project financ-

ing package.

Pan African says the DFS results indicate

excellent recovered grades and gold pro-

duction, attractive financial returns and a

low execution risk, with the DFS results sur-

passing expectations of previous technical

and financial assessments of the project.

The DFS was undertaken by DRA Projects.

The planned commencement date of

the project is January 2017, with first gold

forecast for the final quarter of the 2018

calendar year and full commissioning in

December 2018.

Annual recoverable gold production of

approximately 56 000 ounces is projected

for Elikhulu’s initial eight years of opera-

tions and 45 000 ounces of gold for the

remaining five years thereafter. Optimal

plant capacity for the project allows

12 Mt/a throughput. Current arisings and

inferred gold resources could extend proj-

ect life beyond the DFS estimated life of 13

years. The projected AISC over the life of

Elikhulu is US$523/oz.

Initial capital cost is forecast at approxi-

mately R1,74 billion (US$119,9 million). The

internal rate of return (IRR) (real, post-tax)

is 23,1 %with a payback period of less than

four years, based on an assumed gold price

of US$1 180/oz.

Pan African believes the experience

gained in the construction and operation

of the Barberton Tailings Retreatment

Plant (BTRP) and the Evander Tailings

Retreatment Plant (ETRP) positions it to

successfully execute the construction and

operation of Elikhulu.

The project entails establishing facilities

and infrastructure at Evander Gold Mining,

owned and operated by Pan African, to re-

treat gold plant tailings at a rate of 1 Mt/

month. This is in addition to the existing

production from the ETRP which will con-

tinue to operate independently for the

next 13 years.

Three existing tailings storage facilities

will be reclaimed, in the following order:

Kinross, Leslie and Winkelhaak. Post pro-

Scoping study completed on Lindi Jumbo

Emerging African graphite producer

Walkabout Resources, listed on the ASX,

has announced the results of a scoping

study for a proposed open-pit mine and

graphite processing plant at the 70 % held

Lindi Jumbo graphite project in south-

eastern Tanzania. Project economics are

highly robust as a result of the high grade

nature of the project and the expected pre-

mium natural flake graphite product, says

the company.

The base case employed during the

scoping study was for the development of

a mining and processing operation at Lindi

Jumbo to produce an annual output of

25 000 tonnes per annum of four discrete

products of graphite concentrate for sale

FOB from the Port of Mtwara. Such a level

of production would entail the milling of

only 3 Mt over the 20-year life of mine, an

average of only 150 000 tonnes per annum

(12 500 tonnes per month).

Although the project will potentially

deliver a sought-after premium product

with up to 85 % of the flake graphite in

concentrate above 180 µm, the basket

price used in the scoping study is up to

33 % less than prices used in bankable

feasibility studies conducted by other ASX

companies developing graphite projects in

Africa.

The upside case model considered the

increase of the initial production rate to

40 000 tonnes of graphite in concentrate

per annum. The difference in processing

capacity has already been built into the

plant design and equipment sizing as a

redundancy so minimal additional capital

would be employed. This model has also

been estimated in capex, working cost and

life of mine production to an accuracy level

of cost of ±25 %. Mining production rates

are increased to 260 000 tonnes per annum

or a very modest 21 500 tonnes per month.

Key study outcomes include an oper-

ating cost per tonne in concentrate

estimated at US$290 to US$350 and a pre-

production capex of approximately US$35

million to US$40 million with a payback

period of less than two years.

The base case pre-tax NPV

10

is estimated

to be US$169 million for the 25 kt/a pro-

duction option and US$304 million for the

40 kt/a production option. The pre-tax IRR

estimate is 63 % for the base case and 97 %

for the upside case.

Mineral Reserve Estimation – All Probable

TSF Name Tonnes (Mt) Au (g/t) Au (Moz)

Kinross

47,0

0,31

0,47

Bracken/Leslie

70,1

0,32

0,71

Winkelhaak

70,0

0,24

0,55

Total

187,1

0,29

1,73

cessing, these will be consolidated into

a single enlarged Kinross tailings facil-

ity, contributing to reducing Evander’s

environmental footprint and associated

environmental impact.

Comments Cobus Loots, Pan African’s

CEO: “We are pleased to announce the

positive findings of the independent

Definitive Feasibility Study. Operating

low-cost tailings plants has become an

important business for Pan African in

recent years, and we now intend to pro-

ceed with construction of the Elikhulu

tailings retreatment project. This project

is expected to materially enhance our

Group’s production profile and support

Pan African’s continued focus on low-cost,

high-margin gold ounces. The sub-

stantial capital investment required

demonstrates our commitment to

the South Africanmineral sector and

our shared responsibility of creating

employment and alleviating pov-

erty in the Evander community.

“Our primary consideration in

Pan African approves Elikhulu tailings project

any capital allocation decision is our abil-

ity to successfully execute the designated

project and to generate the required

returns over the investment horizon. The

attractive returns already being earned on

the capital invested in the BTRP and ETRP

bear testimony to our previous success

and will serve as invaluable experience in

completing the project.

“Elikhulu is expected to firmly establish

Pan African as a leader in long-life, low-

cost tailings retreatment, and possibly

unlock other opportunities in the sector.

We expect the project to reduce the Group

and Evander cost profiles and generate

robust cash flows and attractive returns

for our shareholders.”