Table 8.2 Capital Improvement Program

Water System Master Plan

City of Morgan Hill

PRELIMINARY

Pipeline Improvements

Infrastructure Costs

Suggested Cost Allocation

Cost Sharing

Existing Diameter

New/Parallel/

Replace

Diameter

Length Unit Cost

Infr. Cost

Existing Users Future Users Existing Users

Future Users

(in)

(in)

(ft)

($)

($)

($)

($)

($)

Baseline Constr.

Costs

Estimated Const.

Costs

1

Capital Improv.

Costs

2

Improv. No.

Pressure Zone

Alignment

Limits

Construction Trigger

Suggested Expenditure

Budget

Jackson Oaks Pressure Zones

RP-2

Jackson Oaks

Hill Top Ct

From Jackson Oaks Dr to approx 550'

ne/o Jackson Oaks Dr

8

Replace

8

550

180

99,000

99,000

128,700

167,310

2018-2020

Immediate

100%

0%

167,310

0

RP-3

Jackson Oaks

Oak View Ct

From Jackson Oaks Dr to approx 700' s/o

Jackson Oaks Dr

8

Replace

8

700

180

126,000

126,000

163,800

212,940

2018-2020

Immediate

100%

0%

212,940

0

RP-8

Hydropneumatic Zone

Oak Canyon Dr

From Jackson Oaks Hydropneumatic tank

to Jackson Oaks Dr

8

Replace

8

600

180

108,000

108,000

140,400

182,520

2018-2020

Immediate

100%

0%

182,520

0

Subtotal - Jackson Oaks Pressure Zones

333,000

432,900

562,770

562,770

0

Subtotal - Pipeline Improvements 10,919,025 14,194,733 18,453,153

5,214,317 13,238,836

Storage Reservoir Improvements

Proposed Storage Capacity

(MG)

BR-T1

Boys Ranch

Demolish existing 0.55 MG Boys Ranch tank and replace with 1.20 MG tank

Replace

1.20

2,063,412

2,063,412

2,682,436

3,487,167

2026-2030

420 EDUs

30%

70%

1,046,150

2,441,017

GA-T1

Glen Ayre

Demolish existing 0.10 MG Glen Ayre tank and replace with 0.25 MG tank

Replace

0.25

537,347

537,347

698,551

908,116

2021-2025

Immediate

80%

20%

726,493

181,623

ED-T1

Nob Hill

Existing Edmundson tank site

New

0.90

1,934,449

1,934,449

2,514,784

3,269,219

2026-2030

2,350 EDUs

0%

100%

0

3,269,219

WD-T1

Woodland

Demolish existing 0.03 MG Woodland tank and replace with 0.25 MG tank

Replace

0.25

537,347

537,347

698,551

908,116

2021-2025

Immediate

70%

30%

635,681

272,435

HL-T1

Holiday 1

Dunne Ave approx 500' ne/o Flaming Oak Ln

New

0.85

1,826,980

1,826,980

2,375,073

3,087,596

2018-2020

E. Dunne Pump Station 1,

2, and 3 Abandonement

40%

60%

1,235,038

1,852,557

Subtotal - Storage Reservoir Improvements 6,899,535 8,969,395 11,660,214

3,643,363 8,016,851

Groundwater Well Improvements

Proposed Pumping Capacity

(gpm)

BR-W1

Boys Ranch

Burnett Ave

Approx 6,000' ne/o Monterey Ave

New

800

2,340,000

2,340,000

3,042,000

3,954,600

2031-2035

As development

occurs

0%

100%

0

3,954,600

NH-W2

Nob Hill

Butterfield Blvd

400' E of Railroad Ave and Fisher Ave

New

800

2,340,000

2,340,000

3,042,000

3,954,600

2031-2035

As development

occurs

0%

100%

0

3,954,600

Subtotal - Groundwater Well Improvements 4,680,000 6,084,000 7,909,200

0

7,909,200

Pump Station Improvements

Proposed Capacity

(gpm)

NH-PS1

Nob Hill

Dunne Ave and Magnolia Wy

New

3 @ 900 gpm

1,300,533

1,300,533

1,690,692

2,197,900

2018-2020

E. Dunne Pump Station 1,

2, and 3 Abandonement

40%

60%

879,160

1,318,740

HL-PS1

Holiday 1

Dunne Ave approx 500' ne/o Flaming Oak Ln

New

4 @ 550 gpm

1,113,467

1,113,467

1,447,507

1,881,759

2021-2025

Holiday Tank Construction

90%

10%

1,693,583

188,176

Subtotal - Pump Station Improvements 2,413,999 3,138,199 4,079,659

2,572,743 1,506,916

Pressure Reducing Valve Improvements

Proposed Size

(in)

HL-PRV1

Holiday 1

Thomas Gr approx 1,100' w/o Gnarled Oak Ln

New

3

47,300

47,300

61,490

79,937

2018-2020

Holiday Tank Construction

40%

60%

31,975

47,962

Subtotal - Pressure Reducing Valve Improvements

47,300

61,490

79,937

31,975

47,962

Comprehensive Plan Updates

Water System Master Plan Updates (Years 2021, 2026, 2031, 2036)

200,000

-

-

800,000

2021, 2026,

2031, 2036

65%

35%

520,000

280,000

Urban Water Management Plan Updates (Years 2021, 2026, 2031, 2036)

100,000

-

-

400,000

2021, 2026,

2031, 2036

65%

35%

260,000

140,000

Water Rate Study Updates (Years 2021, 2026, 2031, 2036)

100,000

-

-

400,000

2021, 2026,

2031, 2036

65%

35%

260,000

140,000

Subtotal - Comprehensive Plan Updates

1,600,000

1,040,000 560,000