LNG terminal in northern Greece / Alexandroupolis - LNG Section
General Information
Promoter
Gastrade S.A.
Operator
Gastrade S.A.
Host Country
Greece
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
LNG-N-062
GASTRADE S.A.
100%
TRA-N-063
GASTRADE S.A.
100%
LNG-N-062
Project
LNG Terminal
Non-FID
Update Date
20/05/2016
Advanced
Description
Please note that this part refers only to LNG section of the Project, i.e. the floating terminal and its Mooring system. The Pipeline section of the
Project is addressed in TRA-N-063. The project consists of an LNG offshore Floating Storage Regasification Unit, a Mooring & a Pipeline system
(24km Subsea and 4km Onshore), connecting the floating unit to the Greek National Natural Gas System at the area of Amfitriti, 5.5km NE of
Alexandroupolis where, DESFA, the NNGS TSO, will build a metering & regulating station. The floating unit, will be stationed in the sea of Thrace,
17.6km SW of Alexandroupolis in NE Greece, at an offshore distance of 5.4 n.m. from the nearest shore. It will have up to 170.000m3 LNG storage
capacity and a gas send out capacity of 700.000 Nm3/h corresponding to 6.1bcm/y.
Regulatory Decisions and
similar material conditions
No TPA exemption requested NRA only gave opinion on the Independent Natural Gas System License issued by the Ministry of Energy &
Environment on 19.08.2011 (opin. number: 29/2011)
Enabled Projects
Project Code Project Name
TRA-N-063 LNG terminal in northern Greece / Alexandroupolis - Pipeline Section
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Alexandropoulis LNG
Gastrade S.A.
2018
LNG_Tk_GR
GRa
187.5 GWh/d
Comment: Increment available 100% at operation start-up.
Alexandroupolis Amphitriti
Gastrade S.A.
2018
GRa
IB-GRk
268.0 GWh/d
Comment: Increment available 100% at operation start-up.
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM