Previous Page  11 / 44 Next Page
Information
Show Menu
Previous Page 11 / 44 Next Page
Page Background

Mechanical Technology — July 2016

9

Special report

Above:

ABB’s Longmeadow facility now has

a 750 kWp, monocrystalline rooftop PV

system connected to a microgrid.

Above right:

A PowerStore

TM

battery-based

grid stabilising system takes up the load

immediately when the grid goes down.

Right:

The dc power from the panels is

passed through a single PVS 800 630 kW

ABB inverter to generate the ac supply.

and greener power solution

“So while microgrids can be grid con-

nected, as we see at our demonstration

plant here in Longmeadow, they are also

100% ‘islandable’. Here, we have grid-

connected power, PV solar generation,

the battery and diesel generation all

interconnected via a common ring and

automatically managed by the Microgrid

Plus distributed control system (DCS).

The unique feature of ABB’s microgrid

control system is that it has a distributed

network of controllers allowing for redun-

dancy, expandability and maintenance to

take place without interrupting genera-

tion of power.

“As soon as an outage is detected,

the PowerStore provides the reference

for off-grid generation. Then, when the

grid comes back on line, the PowerStore

resynchronises, which will cause the off-

grid generation sources to follow. The grid

can then be safely brought back into the

supply mix,” he adds.

Key features of microgrids

The core purposes of ABB’s microgrid

solutions is power security and grid

resilience. Since no single generation

option is able to offer this all of the

time, it makes sense to combine power

generation sources to make sure power is

always available. “While seamless power

changeover is not always necessary, it is

now a primary part of our offering and is

often essential,” Duarte suggests.

“Probably the largest microgrid market

is in the USA, where you would think

they have no need of it. Why? Because

of the increasing occurrence of natural

disasters, which tend to take out the grid

and cripple the affected community. To

minimise the impact of such events, the

power needs to be restored immediately

and microgrids are being installed on a

redundancy basis to back up the grid in

high-risk areas. Typically these are large

systems of between 10 to 100 MW,

but there is no capacity limit since the

technology involves the management

and coordination of generation, not the

generation itself,” he informs

MechTech

.

A second objective is to achieve the

lowest possible levelised cost of energy

(LCOE) from a combination of generation

sources. “Levelised cost of energy is a

stream of equal payments, normalised

over the expected energy production

period, that would allow a project owner

to recover all costs – including financing

and an assumed return on investment

over a predetermined financial life. This

value is expressed as a tariff per kWh of

generation,” he explains, adding, “gener-

ally calculated for a 20-year life.”

With this information, ABB’s Microgrid

Plus DCS is able to optimally combine

available generation sources to meet

prevailing load demand at the lowest

possible cost.

And the third important imperative