Previous Page  7 / 52 Next Page
Information
Show Menu
Previous Page 7 / 52 Next Page
Page Background

PRESSURE + LEVEL MEASUREMENT

Engineering considerations

For the engineering plant under consideration the main focus for steam

production is to ensure that plant process steam demands are satisfied

and excess steam available for power co-generation is an additional

advantage. Sufficient steam productions are therefore not measured in

terms of available steamfor power generation. In a fluctuatingoff-gas pro-

duction environment that results in fluctuating steam flow productions,

it is to be expected that steam availability for power generation will not

be constant and steam shortages will occur that may lead to unforeseen

turbine trips. It should be noted that a turbine is designed to operate

withinmaximumandminimumallowable steamflow limits. Steamflow

above the maximum capacity is not allowed and cannot be utilised by

the turbine. However, when the steam flow drops below the minimum

allowable limit, protectionmeasureswill immediately shut down the inlet

steamvalves to the turbine tripping themachine instantly. Theminimum

steam flow limit helps to protect a turbine against damaging vibrations.

Figure 2

demonstrates hypothetical steam flow productions from

fluctuating off-gases over an arbitrary 100 hours’ time interval, where

the fluctuating curve represents steam flow production (m.

total

) in the

boiler houses and the constant 50 ton/h line denotes plant usage

(m.

usage

) demands that need to be satisfied. The area between the two

curves denotes excess steam available for power co-generation. As

mentioned, plant steam demands are not constant and only chosen as

such for illustrative purposes. If all of the excess steam from

Figure 2

are utilised for power co-generation, the maximum average rate of

power co-generation can be calculated by integrating the product of

the area between the two curves with a conversion factor (C

f

) and given

by (1). This conversion factor is a function of the isentropic efficiency

of the turbine, which in turn is a function of the steam flow.

Some investment questions need to be addressed regarding the

quantity of turbines and at what capacities need to be procured for

power generation purposes. As mentioned above, this article does

not address any investment questions and will only demonstrate the

potential power co-generation effect if off-gas flaring is regulated.

Figure 2: Hypothetical steam flow production over time.

The hypothetical residual steam from

Figure 2

is taken and plotted in

Figure 3

with the addition of a turbine’s operating limits. The two con-

stant lines represent the minimum and maximum allowable steam

flow limit of the turbine. All steam flow above the maximum limit

(30 ton/h) cannot be utilised by the turbine and for every instance

that the steam flow drops below the minimum limit of 10 ton/h, the

turbine will trip if in operation. It should be noted that when power

co-generation takes place in such fluctuating steam flow conditions,

protection measures are in place to protect a turbine from tripping

in close proximity. Common engineering practice is to allow for a

time of steam stability, i.e. a continuous time interval before start-up

where steam flow must be sufficient to have kept the turbine opera-

tional. Under such protectionmeasures

Figure 3

does not necessarily

imply that six turbine trips would have been experienced within the

100 hour time period. Note that when a turbine is not operational,

all power generation capability of the steam goes to waste, since it

cannot be stored and utilised at a later stage.

Under fluctuating steam availability steam shortages are ex-

pected, however, trips should be limited as far as possible, since a

turbine is designed to operate continuously and each trip occurrence

depletes the life expectancy of the machine.

The scenario as depicted in

Figures 2

and

3

displays a situation

where plant steam usages cannot be altered to assist turbines dur-

ing low steam flow availability. The generic layout given in

Figure 1

shows that parallel to off-gas steam production in boiler houses,

off-gas flaring takes place. Thus, if plant steam usages cannot adapt

to assist power co-generation, an investigation into off-gas flaring

might prove to be advantageous.

Figure 3: Hypothetical steam flow available for power co-generation over

time, with turbine operating limits.

The following section displays simulation results for the engineering

plant where co-generation exists under conditions described in this

section. Measured steam productions and plant usages are used to

display power co-generation capabilities. An investigation is then

launched into the off-gas quantities that were flared, from obtained

measurements, and how the regulation of this flaring could poten-

tially have impacted power generation at this plant. As mentioned,

power co-generation is only selected to stipulate the effect of off-gas

flaring and therefore simulations where boiler house capabilities are

hypothetically increased to observe an even more positive power

co-generation effect will not be discussed. All simulations are per-

formed with the optimisation model from [2].

120

100

80

60

40

20

0

120

100

80

60

40

20

0

0 2 0 4 0 6 0 8 0 1 0 0

0 2 0 4 0 6 0 8 0 1 0 0

Time (h)

Time (h)

Total steam production (ton/h)

Excess steam (ton/h)

W

max

= ▒〖

C

ƒ

(m

total

– m

usage

)dh〗

(1)

100

0

5

June ‘17

Electricity+Control