Previous Page  9 / 52 Next Page
Information
Show Menu
Previous Page 9 / 52 Next Page
Page Background

Figure 7: Total potential steam productions flared to atmosphere.

As mentioned, the boiler houses consist of a maximum steamproduc-

tion capacity of 260 ton/h. Furthermore, for line pressure control to

ensure that air does not enter the off-gas pipelines, which are open to

atmosphere, a certain quantity must always be flared. It is therefore

never possible to utilise all the energy potential from the off-gases.

Figure 8: Potential steam productions flared to atmosphere that could

have been realised.

Influence of regulating off-gas flaring percentage

It was mentioned earlier that management was under the impres-

sion that off-gas flaring was regulated to be 10% of the volume flow,

whereas in the previous section it was reported that on a volume

basis 46,9% of the off-gases were flared. Five different off-gas flaring

scenarios are chosen that range from 40,0% down to an optimistic

5,0%. For each scenario the potential steam that could have been avail-

able are calculated and simulations are performed by means of the

mathematical model. The power co-generations are given in

Table 2

.

Table 2: Turbine simulation results for various off-gas flaring percentages.

Flare %

Max Potential

Power

Generation

[MW]

Combined

Power

Generation

[MW]

Trips

46,9

21,4

20,5

18

40,0

25,2

23,1

25

30,0

30,1

27,0

20

20,0

33,4

29,7

15

10,0

35,0

30,8

13

5,0

35,5

31,4

11

From the results in

Table 2

it can be seen that if off-gas flaring was

controlled, significant increases in power co-generation could poten-

tially have taken place. Allowing for only 10,0% of flaring, the potential

power co-generation could increase with up to 50,0% with a reduced

PRESSURE + LEVEL MEASUREMENT

number of combined turbine trips. Even though sufficient steam

is mostly available to operate both turbines at maximum capacity,

turbine trips cannot be eliminated, due to instances of low off-gas

productions as seen in

Figure 7.

In

Table 3

the time percentages are displayed for both T

1

and T

2

,

for all of the different steam flow scenarios, where power co-gener-

ation occurs at maximum capacity and for when the turbines are in

trip. The results show, as expected, that when the flaring percentage

reduces, turbines will operate more frequently at maximum capac-

ity with less time in a tripped state. The reported values in

Tables 2

3

do not show significant changes when the flaring percentage is

lowered from 10,0% to 5,0%. The conclusion to be drawn is not that

there exists a flare percentage where after improved flaring control

does not increase energy utilisation, but that the combined boiler

houses’ capacity is the limiting factor. This correlates with what was

seen in

Figures 7 and 8.

Table 3: Time percentages for turbines operating at full capacity or be-

ing in trip.

Time % for

Maximum Operating

Capacity

Time % for

Turbine in

Trip

Flare % T1

T3

T1

T3

46,9

5,1

21,7

20,0

14,0

40,0

18,0

38,4

15,2

17,0

30,0

37,0

63,4

7,7

15,1

20,0

52,4

78,0

8,2

9,7

10,0

60,2

82,7

7,0

6,4

5,0

62,0

84,4

8,2

3,7

Taking this information into account, it will make sense to simulate

scenarios where the combined boiler houses’ capacity is increased

to further investigate the effect on power co-generation for this

engineering plant.

With an increase in steam production capabilities additional tur-

bines will have to be added for the simulation model or the operating

limits of T

1

and T

2

should be increased.

Conclusion

An engineering works that produces and utilises fluctuating burn-

able off-gases during normal plant operations was investigated.

The residual off-gases that are not used for plant process purposes

are used to generate steam, in boiler houses, and the remaining off-

gases are flared to atmosphere, nullifying the energy potential. Steam

flow productions are necessary for a variety of plant processes and

these usages may fluctuate over time. Once all plant steam demands

are met, excess available steam is utilised for power co-generation

through the use of steam turbines.

References

[1] E. Vine (2008). Breaking down the silos: the integration of energy

efficiency, renewable energy, demand response and climate

change. Energy Efficiency 1, pp 49 – 63.

350

300

250

200

150

100

50

0

350

300

250

200

150

100

50

0

0 500 1000 1500 2000 2500

0 500 1000 1500 2000 2500

Steam flow (ton/h)

Steam flow (ton/h)

Time (h)

Time (h)

7

June ‘17

Electricity+Control