Previous Page  8 / 52 Next Page
Information
Show Menu
Previous Page 8 / 52 Next Page
Page Background

Table I: Relevant turbine information.

Turbine

number

Maximum

Steam Limit

[ton/h]

Minimum

Steam Limit

[ton/h]]

Conversion

Factor C

ƒ

T

1

(10,0 MW)

55,0

16,5

10/55

T

2

(25,0 MW)

137,5

33,0

10/55

Simulation results

A number of simulations were performed on the power co-generation

capabilities of the engineering plant that utilises residual off-gas for

steam productions. The aim was not to simulate what capacity size

turbine or combination thereof will yield the best power genera-

tion, but to demonstrate the effect that off-gas flaring control could

potentially have on the outcome of a plant’s power co-generation.

The excess steam that was available by the plant during the time of

investigation is plotted in

Figure 4.

Fluctuations with low steam flow intervals are clearly evident

in

Figure 4.

To determine the total power generation potential if

all of the steam could be utilised, (1) is used. All the relevant

turbine information used for the simulations can be found

in

Table 1

, i.e. turbine capacities, steam flow limits and

the conversion factor. For simplicity the conversion

factor is chosen to be equal for both turbines and

constant for all of the operating points. The first

set of power co-generation results are that of the

plant for the initial steam flow profile that will be

used as basis for comparison purposes.

Figure 4: Available steam flow for power co-generation.

Simulations for initial available steam flow

The numerical integral was determined for the initial steam flow as

depicted in

Figure 4

and the maximum average rate of power co-

generation was calculated at

.

W

max

= 21,4 MW. The combined power

co-generation from turbines T

1

and T

2

equals 35,0 MW and will be

used for all steamflow scenario simulations with the combined boiler

houses’ capacity of 260 ton/h. Power co-generation results obtained

for T

1

and T

2

are plotted in

Figures 5

and

6

respectively. Turbine trips

due to steam shortages are evident in these two figures and, further-

more, that both T

1

and T

2

operate mostly below the maximum limits.

T

1

only operates at maximum capacity for 5,1% and T

2

for 21,7% of

the time. The total combined average rate of power co-generation is

20,5 MW out of a potential of 21,4 MW and simulation results show

18 combined trips for the turbines during the time period.

250

200

150

100

50

0

PRESSURE + LEVEL MEASUREMENT

Figure 5: Simulated power co-generation for 10,0 MW under initial

available steam flow.

Investigating the flaring of off-gases

Flared off-gas measurements were obtained for the time period and

the total potential flared steam were calculated and plotted in

Fig-

ure 7

. When

Figure 7

is compared with

Figure 4

it can be seen that a

significant amount of potential steam is flared into the atmosphere

where the energy potential is wasted. Calculations showed that 55,2%

of all energy potential in the residual off-gases were flared, resulting

in only 44,8% usage of this energy resource. The 55,2% correlates to

a 46,9% combined off-gas volume flow that was flared. Take

note that the low off-gas flaring instances correspond to

low steam flow production occurrences and even if

all available off-gases were to be used to generate

steam, low steam availability periods would still

have existed. However, even though it is evident

from

Figure 7

and these percentages that significant

quantities of potential steam generation does not

take place, it is not yet possible to comment on how

this could potentially affect the power co-generation.

Figure 6: Simulated power co-generation for 25,0 MW under initial

available steam flow.

In order to investigate how power co-generation could have been

improved due to less off-gas flaring, the potential steam that could

have realistically been generated must be calculated, i.e. taking into

account the total steam generated as well as the combined boiler

houses’ capacity. The potential steam that could additionally have

been generated during this time can be seen in

Figure 8. Figures 7

and

8

have been plotted on the same y-axis intervals to demonstrate

the difference between the potential steam flow that was flared

against the maximum additional steam flow that could potentially

have been produced. These plotted results further indicate that

significant steam flow productions cannot take place due to boiler

house capacity restrictions.

30

25

20

15

10

5

0

0 500 1000 1500 2000

0 500 1000 1500 2000 2500

Time (h)

Power generation (MW)

Time (h)

12

10

8

6

4

2

0

0 500 1000 1500 2000 2500

Power generation (MW)

Time (h)

2500

Electricity+Control

June ‘17

6