Background Image
Previous Page  32 / 56 Next Page
Information
Show Menu
Previous Page 32 / 56 Next Page
Page Background

DIAMONDS

30

MODERN MINING

October 2015

reducing the overall diamond resource grade

from 33 to 28 carats per hundred tonnes (cpht)

and the total diamond resource carats from

29,7 to 23 million carats (Mct). As a result the

undiluted mine plan grade has reduced from

32 cpht to 27 cpht, thereby resulting in a 17 %

reduction in the overall carats recovered over

the mine plan, which is partially offset by an

increase in the diamond price as described

below. When combined with the reduced waste

stripping associated with the new split shell

mine design, the favourable rand/US dollar

exchange rate and the changes to the modelled

cash flow, the overall rand revenue per tonne

for the mine plan has improved.

As indicated above, a split shell design has

been adopted for the open pit. Advantages of

this approach include a reduced

risk of ramp failure (once two

splits join then a concentric ramp

results), lower capex for the ini-

tial mining fleet (due to lower

waste) and less in-pit traffic con-

gestion with multiple ore and

waste faces available.

The stay in business capital

and operating costs for the proj-

ect have also been reviewed in

detail and, taking into account

inflation, better cost definition

and risk mitigation, they have

increased in rand terms by R323

million and R1,9 billion respec-

tively. Following the devaluation

of the rand against the US dollar

(R10:US$1 used in the 2013 DFS

versus R13,27:US$1 used in the

mine plan), this translates to an increase in stay

in business capital of US$20,6 million and a

decrease in operating costs of US$56,8 million.

These changes have been included to reduce

the overall risk of delivering the mine plan.

The 2013 DFS used a base case average

diamond price of US$107/ct with an upside

average large stone potential of US$156/ct

both at a 1 mm BCO. In preparation for defin-

ing parameters for running the mine plan,

independent consultants were appointed to

re-price the Liqhobong pilot plant produc-

tion parcel and compile an updated August

2014 US$/ct diamond revenue estimate. The

2014 US$/ct revenue estimate was based on

a combination of modelled size frequency

distributions (SFD) per facies and modelled

Main plant terraces: -6 m,

0 m and +8 m (September

2015).

Open pit design. Overall

basalt slope angles range

from 50 to 55 deg. Kimber-

lite angles range from 40 to

46 deg.