Background Image
Previous Page  37 / 56 Next Page
Information
Show Menu
Previous Page 37 / 56 Next Page
Page Background

October 2015

MODERN MINING

35

feature

T

he 62-month, R4,6 billion multi-

disciplinary greenfield project in

the Secunda area had an integrated

management team at its helm. The

Joint Venture’s multi-disciplinary

team had to interface with the Sasol project

team, the Sasol Mining team and the Sasol

Coal Supply team, which would ultimately

run the entire operation and therefore had to

be brought up to speed with the project’s tech-

nical scope.

“The constructed project demonstrates our

commitment to sustainable engineering solu-

tions,” comments Kevin Seyfried, Director

Mining AEM, Associate at Hatch Goba.

“Specialised package managers were respon-

sible for the total delivery within their areas of

responsibility.”

The basic engineering design packages

ensured suitability, functionality, constructabil-

ity, operability and maintainability of the new

mining infrastructure and associated materials

handling system. All the systems were designed

Night view of Impumelelo, a new 8,5 Mt/a replacement tonnage coal mine complex in the Secunda area.

The 15 000-tonne coal

bunker at Impumelelo under

construction.

Impumelelo

commended

for

engineering excellence

The Impumelelo shaft project at Sasol Mining’s Brandspruit mine received a commendation

at the CESA Aon Engineering Excellence Awards 2015 for the RSV ENCO Hatch Goba Coal

Joint Venture. Sasol Mining appointed the Joint Venture as the Engineering, Procurement and

Construction Management (EPCM) consultant in August 2009.

to be energy efficient and optimised within

strict coal degradation and spillage tolerances.

A techno-economic review of the project’s

feasibility was completed by the Joint Venture

in June 2009, followed by a detailed engineer-

ing design phase from July 2009 to December

2010. Construction began in earnest in June

2011. Phase 1 construction was completed

in June 2015, with Phase 2 scheduled for

completion in June 2019. Upon completion,

Impumelelo will have 13 production seams,

with a total shaft depth of 235 m.

Impumelelo is a new 8,5 Mt/a replacement

tonnage coal mine complex for Brandspruit in

the Secunda area of Mpumalanga. The project

scope entailed the design and development

of the complete greenfield mine complex.

Therefore special consideration had to be paid

to the build-up of the new operation, in con-

junction with the phasing out of the existing

coal-mining operation.

It included the entire shaft system of two

vertical shafts, a decline shaft and associated

COAL MINING