Background Image
Previous Page  36 / 64 Next Page
Information
Show Menu
Previous Page 36 / 64 Next Page
Page Background

34

CONSTRUCTION WORLD

NOVEMBER

2015

'Cross Hole Sonic Logging' (CHSL) tubes and extended into the pile cap.

"Exceptionally robust 36 mm Thread Bar steel rods (TB950) were

then inserted by overhead crane into the micropile anchors for added

stability. Ultimately, each micropile reached a depth six metres below

the pile toe and were grouted at 40 Mpa at a final depth of 20 metres,"

Tshivhinda added.

All of these relatively voluminous and intricate components were

housed in specially-designed 13 m long steel cages, with a diameter of

800 mm and weight of 1,8 tons each. To accommodate the wide cages,

900 mm diameter piles had to be drilled by Gauteng Piling, which used

two of its Williams diggers for the Kagiso contract.

Prior to the start of the piling contract, the company commissioned

by the contractors to handle the geotechnical investigations had drilled

four large diameter auger trial holes in a grid pattern on the site, spaced

about 30 m apart, with a Soilmech hydraulic drilling rig hired from

Gauteng Piling. "The holes were drilled to refusal on very soft, to soft,

basaltic lava rock and showed that the maximum depths that could

be reached before refusal were from 9,1 metres to 13 metres. Ground

water was encountered at a depth of 11 metres, and therefore Gauteng

Piling had to employ the drill-and-cast method of piling for the entire

contract. This form of piling calls for a concrete truck on standby right

next to the drill rig so that concrete can be cast immediately after the

drilling flights are extracted to the surface. This prevents water ingress

and collapse of the piles," she stated.

PROJECTS AND CONTRACTS

The contract, awarded to the MBA North member company

by the developer, BUA Africa Properties, called for 100 auger

piles with an average depth of 13 metres to serve as foun-

dations for the 240-unit Kagiso residential development in

Margaret Avenue, Kempton Park.

Rofhiwa Tshivhinda, site manager for Gauteng Piling, says the piles

– spread over an area of 3 000 square metres on which an existing struc-

ture had been demolished - were successfully excavated and installed

by the company over a five-week period.

"For a multi-storey building of this nature, rising high above neigh-

bouring structures – and therefore subjected to high structural bending

and horizontal forces – exceptionally strong piling was required. It was

therefore decided that the two lift shafts, on extreme ends of the apart-

ment block, would act as shear walls to stabilise the entire building.

This meant that these two lift shafts had to have piles providing

the utmost foundations and stability. It was therefore decided to

strengthen the 18 piles underneath the lift shafts by inserting five addi-

tional micro-piles (piles-within-piles, so to speak) into these structur-

ally critical foundation elements. The micropiles were drilled through

Project requires

PILES-WITHIN-PILES

Leading piling contractor, Gauteng

Piling, had to provide unusually intricate

and robust foundation piling for the

construction of a new 11-storey apartment

block in the Kempton Park CBD.

>

LEFT:

Exceptionally long steel

rods were lofted over the piles

by overhead crane and then

manually guided deep into place

into the micropile anchors for

added stability.

ABOVE:

Each micropile reached a

depth six metres below the pile

toe and were grouted at 40 Mpa

at a final depth of 20 metres.

Pictured: grouting being poured

into a micropile.

RIGHT:

Steel rods inserted into

micropiles.

"For a multi-storey building of this nature, rising

high above neighbouring structures – and therefore

subjected to high structural bending and horizontal

forces – exceptionally strong piling was required.