36
CONSTRUCTION WORLD
NOVEMBER
2015
PROJECTS AND CONTRACTS
>
With due processes finalised, global
construction and management
consultants Turner & Townsend
have been appointed by Bombela
Concession Company as project managers to
manage this prestigious turnkey expansion
project. The duration of the construction
project is approximately 12 months with antic-
ipated completion by mid 2016.
Bombela says the expansion of the
Gautrain Station platform at the OR Tambo
International Station will allow the current
horizontal two-car system for the airport line
to be increased to at least four rail cars.
The airport platform extension works will
inevitably increase system capacity and
forms part of a medium to long term plan to
attract more users onto the Gautrain System.
Noluthando Molao, associate director of
Turner & Townsend, says construction itself
will be carried out with pre-cast elements
and with the establishment of a storage area
for materials close by, in order to minimise
activity on site. An interesting aspect of the
project is that the tower crane to be used
on site is one of the biggest in the country,
which can lift 32 tons at a radius of 27,8 m
and can pick up a maximum load of 20,6 tons
at a radius of 40 m. Initially procured for the
Medupi Power Station, the crane will be relo-
cated to the OR Tambo construction site.
“One of the key challenges of the project
is that the trains must be fully operational at
all times to ensure there is no disruption to
the Gautrain service.
Coupled with this, the construction is
being carried out at approximately
18 metres above ground level, with the
access road directly beneath the construc-
tion site needing to remain operational
as an airport entry point. What makes the
construction more challenging is that the
crane can only operate from one side of
the viaduct structure and safety will be a
key priority.
“Furthermore, the close proximity of the
City Lodge parking facility right next to the
construction site presents another challenge.
Noise and dust will be minimised
with most of the work being completed
off site and the use of acoustic boards,
while construction will only be under-
taken during specific times as agreed.
“Given the issue of cable theft, the safety
and security management systems require
that the highest security measures are in
place at all times.”
The design and construction in terms
of the project incorporates a number of
aspects which include extending the existing
roof canopy, and – with the use of precast
concrete slabs – horizontally increasing
either side of the platform as well as
extending the platform length by a total of
55 metres. In addition, the concrete parapet
wall will be extended and two fire escape
towers constructed.
Adds Molao: “Not surprisingly, the
contractor tender process had a technical
requirement for a grading of nine, which is
the highest level according to the Construc-
tion Industry Development Board. A BEE
Level 3 minimum requirement was also
stipulated and the successful contractor,
Stefanutti Stocks, will have to achieve 80% of
the scorecard for technical criteria.
Turner & Townsend has considerable
experience in rail and other major transport
programmes, having worked on a number
of projects with Intersite Asset Investments,
a subsidiary of the Passenger Rail Agency of
South Africa (PRASA).
The OR Tambo Station platform expan-
sion is one of a series of projects that Turner
& Townsend has recently been involved in
with Bombela. These include the extension
of Gautrain parkades, parking garages and
additional parking at Midrand and Rhodes-
field Gautrain Stations.
At King Shaka International Airport
in KwaZulu-Natal, Turner & Townsend
were involved as bid managers as well as
programme manager and project managers
for the pre and post contract works for this
modern ‘greenfield’ development. They also
provided procurement advice and training to
the building and civil contractor.
Globally, and with a network of 90
offices, Turner & Townsend has an extensive
track record in major projects, and more
specifically in the air sector having helped
formulate and implement the agreement for
the build of British Airways Terminal 5
at Heathrow Airport (the biggest free-
standing structure in the UK) and playing
an integral role in bringing the project in
on time and on budget.
Turner & Townsend has also been
involved in providing master planning,
procurement strategy and risk manage-
ment services for the development of the
new three-runway system at Hong Kong
International Airport and delivering cost
estimating services, scheduling and risk
management for the expansion of Abu Dhabi
International Airport.
AIRPORT GAUTRAIN STATION
expansion announced
Recently the Gauteng MEC
for Roads and Transport,
Dr Ismail Vadi, announced
that the Gautrain Station
platforms at OR Tambo
International Airport would
be expanded, enabling
passengers to embark
or disembark from a full
four-car train set, which
is currently limited to two
cars. This is subject to future
operational consideration
and implementation.




